So after massive rainstorms producing 4 inches of rain overnight the other night, there was a lot more erosion to our hole undermining our deck. Two of the concrete piers supporting the stairs are now exposed. The pool builder decided to build temporary supports for the deck.
I built some makeshift water barriers out of tarps to keep water from pouring down the hill directly onto the collapsing edge. I really hope this works. Unfortunately, we have much more rain to come this week. We were supposed to do Gunite middle this week and I’m not sure if it will get done because of the rain. I’m getting pretty nervous. We need to hurry and get backfill ASAP.




I built some makeshift water barriers out of tarps to keep water from pouring down the hill directly onto the collapsing edge. I really hope this works. Unfortunately, we have much more rain to come this week. We were supposed to do Gunite middle this week and I’m not sure if it will get done because of the rain. I’m getting pretty nervous. We need to hurry and get backfill ASAP.