Pool Reno....

Burfcr

Bronze Supporter
May 5, 2018
101
Earth
Welcome to the new year and work continuing on the project. Luckily we have had very, very little snow in southern Ontario so work can continue on the spa. Busy day of getting the forming done for the concrete pour for the spa coping. Before the pour is done though, a structure will be built over the spa so that they can heat it and continue work. Measurements and final deck design have been completed too so that they will be ready for that pour in April....

January 4 - Day #30 | Nest
 

Burfcr

Bronze Supporter
May 5, 2018
101
Earth
They are so meticulous! They were a great find to do this work for you!

Is the pool water ice? It looks like it burrrrrrrrrrr

Kim:kim:

Yup - there is a thin layer of ice on the surface of the pool (it was starting to warm up on Thursday so the ice started moving around with the wind).
 

Burfcr

Bronze Supporter
May 5, 2018
101
Earth
With the deep freeze and our first significant snowfall coming later this week, the PB has built the structure over the spa so that it can be heated with work continuing over the coming weeks. Never really thought I would see this as part of the project!!

January 14 - Day #31 | Nest
 

Burfcr

Bronze Supporter
May 5, 2018
101
Earth
How are things going? Is the spa hut working?
Its going slowly. We have hooked up the electrical to the pool shed and have run a line into the spa hut. Just waiting for them to install the baseboard heaters and continue work. So not a ton has happened over the past few days.

As we look forward to spring, we have signed a contract with a local landscape company to help out with the backyard "softscape" and also the shape of the pool deck. Measurements and elevations for the backyard will be taking place this week and we hope to get plans the following week. It will be spring before we know it!