Admittedly, I've only had one gunite pool built, and the equipment went in immediately after the plumbing was done. It was put under pressure and left for leak monitoring from that point, though trench fill, decking, plaster, fill and till turned on.It's been raining lightly last night and this morning. Acid wash workers are supposed to come today to clean the pool, slurry tank and trash.
How long can the plaster be left exposed before it has to be filled? Afterwards, how long can it go before the pumps have to be up and running?
Most of the equip is here (except the builder has the heat pump).
How long can things wait before I need to be concerned?