The next step is doing the horizontal surfaces. They may do that over the next couple of days (not entirely sure). After that they could totally finish the plumbing, gas work and electrical in the pool shed and we can get that tub filled!
We have also done the deal with the landscaping company. They will come in and remove all of the trees that need removing and will also dig out the new areas for the deck. The PB will then come back, pour the deck and will then turn his attention to the pool (wants the deck done first so no damage is done while pouring the concrete decking). The pool will involve the new tiles, grout and then plaster. I think he mentioned putting a structure up over the entire pool during the plastering process so that its a controlled environment (no rain, bugs, bird droppings, leaves, etc). Then once the pool is done, the landscaping crew comes back in to finish everything up (fire pit, plants, trees, bushes, irrigation, re-leveling the backyard, sod, etc.). In my optimistic head, we are wrapped up by the Victoria Day long weekend.