General update below for anyone that cares, but I have a couple quick questions as I complete my inventory of the equipment. I will be opening all the boxes and making sure the right stuff is in there and nothing looks damaged to the untrained eye.
I've had a lot going on since last post. Finished my last day gainfully employed on 7/7 (I am now officially retired but it doesn't feel like it!), loaded up a POD to move cross country on 7/17, visited in-laws in Illinois, drove to Ohio to visit with my parents, drove to Atlanta to watch my son defend his thesis for his PhD in Chemistry on 7/26, drove to Arizona and arrived at our new home on 7/29. Unloaded the POD and spent the last three weeks unpacking, arranging, hanging stuff on walls and getting our new build home to feel more like a home. I need a diversion, so I decided to get the pool work started.
On the plumbing, I've made minor tweaks and now on Rev 7. I decided to go with the larger 2.5-3" 3-way diverter valves for the header (thanks @mas985, the less noise part of your comment did it for me). I left the 2-way valves for the skimmers at 2-2.5" (those won't approach high flow rates unless one skimmer is out of commission).
I have the layout scheduled for Sept 1st and the excavator on Sept 5th. I am very excited to get it started and hope the non-existent monsoon doesn't decide to get started as soon as I open up the earth (I fully expect a 100-year storm to start at the exact wrong time). Had a pre-site with the excavator today to confirm various excavator access widths and discuss what additional access grading will be needed. The anticipation of starting after so many years of dreaming and planning feels like what I remember Christmas was like as a little boy.
- Should I pull all the documentation/paperwork for all the equipment or leave that for the plumber? I think I'm going to pull it as it may "disappear" when the plumber does his thing.
- Any other words of advice as I check everything out?
On the plumbing, I've made minor tweaks and now on Rev 7. I decided to go with the larger 2.5-3" 3-way diverter valves for the header (thanks @mas985, the less noise part of your comment did it for me). I left the 2-way valves for the skimmers at 2-2.5" (those won't approach high flow rates unless one skimmer is out of commission).
I have the layout scheduled for Sept 1st and the excavator on Sept 5th. I am very excited to get it started and hope the non-existent monsoon doesn't decide to get started as soon as I open up the earth (I fully expect a 100-year storm to start at the exact wrong time). Had a pre-site with the excavator today to confirm various excavator access widths and discuss what additional access grading will be needed. The anticipation of starting after so many years of dreaming and planning feels like what I remember Christmas was like as a little boy.