New pool build - Owner-builder

debuda

Bronze Supporter
May 16, 2019
107
Los Angeles
Hi everyone,

I'm just posting my pool build so far. We are in the LA area. Decided on a 16x40 pool with a 6" raised spa (7x7).
For pool equipment we went with Pentair for pumps (3 hp VS, 1 hp booster pump), cartridge filter, heater (400k), and control center (easytouch 8).
Plumbing: Pool and spa circulation plumbing: (3) return lines on 2.5” line, vacuum line 1.5” line, 2 skimmers on 3” line, spa suction on 2.5” , and spa return on 2.0”, 3/4” fill line for intelli level
So far we have completed the excavation, rebar, rough plumbing and electrical and shotcrete. We are going to start next week with the pool deck and coping. Once we pass inspection there its on to tile, finish plumbing and electrical, installing gates and finally plaster!!

Hope we can get through the rest in the next month or so. We would love to have the pool opened for Summer.

Here are some pics of the build so far....
 

Attachments

  • 20190402_113458.jpg
    20190402_113458.jpg
    768.7 KB · Views: 163
  • 20190407_140337.jpg
    20190407_140337.jpg
    659.2 KB · Views: 167
  • 20190410_172249.jpg
    20190410_172249.jpg
    598.5 KB · Views: 173
  • 20190411_180421.jpg
    20190411_180421.jpg
    696.5 KB · Views: 177
  • 20190417_171213.jpg
    20190417_171213.jpg
    578.6 KB · Views: 172
  • 20190419_073158.jpg
    20190419_073158.jpg
    516.3 KB · Views: 168
  • 20190419_073222.jpg
    20190419_073222.jpg
    535.6 KB · Views: 172
  • 20190502_074731.jpg
    20190502_074731.jpg
    552.4 KB · Views: 187
  • 20190527_074809.jpg
    20190527_074809.jpg
    548.4 KB · Views: 182
LOVE, LOVE, LOVE that tile right there!!! That will be so pretty!

Plaster color--------the darker you go the more prone to mottling it may be. Just something to think about. Here is a thread that was started to share different plaster colors. This might help you:

Kim:kim:
 
LOVE, LOVE, LOVE that tile right there!!! That will be so pretty!

Plaster color--------the darker you go the more prone to mottling it may be. Just something to think about. Here is a thread that was started to share different plaster colors. This might help you:

Kim:kim:
We hope it all comes together in the end. So many option and styles.
Thanks for the link!

You think pebble is still prone to mottling. One of the reasons we want pebble is to prevent mottling.
 
  • Like
Reactions: chemillion
I have a set of links to help you get the best plaster possible. It is a lot of info but worth looking over.
Ten Guidelines for Quality Pool Plaster Best one of all
All Plaster Finishes Should Last 20 Years
Not All Color Pigments are Good for Pools How to pick a good color for plaster.
A Plastering 'Watch List' | Professional Watershaping | Watershapes
Trouble Free Pool
Trouble Free Pool

Any plaster can mottle. It all comes down to the crews skills, experience, care, etc.

Kim:kim:
Thanks for all that info!
Hoping my plaster guy knows what he's doing!
 
Another pic for now with coping and tile in.
We have deck coming pour tomorrow.

We decided on this tile in the end.

Hope the decking and coping work out together. Coping we chose the Davis color Outback and we are installing Mocha for the decking.

Will post picks once it's all cured.

We're have gates inspection next.
Any thoughts on fencing? We are looking at a 5' high mesh fence vs a metal (aluminum or iron) fence.
 

Attachments

  • image000000_01.jpg
    image000000_01.jpg
    804.4 KB · Views: 162
  • Like
Reactions: chemillion
That tiling and coping came out GREAT! I LOVE the tile you picked out!!! PRETTY!!

Make sure they put some kind of "chair" under the wire to hold it up. Do NOT let them pour unless they are there. They may try to say "We will hold it up as it is poured"!! It will sink back down when they let it go :( If it stays on the bottom like that it will not do any good for your decking.

Kim:kim:
 

Enjoying this content?

Support TFP with a donation.

Give Support
Ok have a few more pics to share...

Plumber came by today and installed all the equipment and electrical!

I was a little concerned that the heater and filter are not bolted. Is that normal?

Next is fence and then plaster!! Cant wait!
 

Attachments

  • image000000_03.jpg
    image000000_03.jpg
    629.1 KB · Views: 168
  • image000000_02.jpg
    image000000_02.jpg
    382.5 KB · Views: 168
That looks great!!!

The filter does not need to be bolted down. I don't THINK the heater does not need to but will call in someone who will know for sure. @bdavis466

Kim:kim:

Thanks!! Excited seeing it all come together!!
And thanks for the call out.

Pool build is looking great! Looks similar to our build but yours is going much faster. I like the color of the coping you selected.

Thank you! We spent many months planning and we really moved in the beginning but slowed down after we had the shotcrete placed because I didnt line up any subs for the finish work. It's been about three months in total.
 
Honestly I don't think it needs to be bolted down but I failed a final inspection because of that. I would imagine the inspectors are quite particular in LA...

With the earthquakes and all they are very particular especially when it comes to gas appliances.
I didnt even see a place to bolt down the heater.
One thing I brought to the attention of the plumber was that he installed the gas line before the earthquake gas shutoff valve. He told me that as long as its outside it's no problem (that still doesnt give me any peace of mind!).

I guess I'll find out when they come to inspect but would live to pass on the first go round.
 
Same here, everything went quick until after the gunite was finished. Then all the tile, masonry, and paver work seems to be dragging on and on. Many LONG breaks from 1-2 weeks at a time. In June, they worked 6 out of 20 workable days. They finally came today to work! Suppose to be here all week. We’ll see how much gets done before the next long break.
 
Same here, everything went quick until after the gunite was finished. Then all the tile, masonry, and paver work seems to be dragging on and on. Many LONG breaks from 1-2 weeks at a time. In June, they worked 6 out of 20 workable days. They finally came today to work! Suppose to be here all week. We’ll see how much gets done before the next long break.

Looks like you dont have too much more to go. Hope they will get it done this month!! What kind of plaster are you going with?
 