Doing BYOP. Done with excavation, rebar, plumbing. 2 Questions though. The plumber dug these trenches for the PVC but then didn't back fill it. we are planning to do pavers, who is supposed to backfill the yard to prepare it for decking? Do I do that after gunite (hopefully this weekend) and electrician are done with their stuff? Is that something I call the excavation company back for?
Also when the plumber was making the trenches, he knocked out a few of the pool beams, like behind the skimmer in the pic below. Is that going to be a problem for gunite? do I need to have the plumber come back and fix it or is that pretty normal?
Also, with all the plumbing sticking out into the pool, who actually cuts everything off and levels it, installs the fittings etc. Is that the plaster company?
Sorry, sitting here trying to figure out what sub contractors I still need to finish the job. Pics below


Also when the plumber was making the trenches, he knocked out a few of the pool beams, like behind the skimmer in the pic below. Is that going to be a problem for gunite? do I need to have the plumber come back and fix it or is that pretty normal?
Also, with all the plumbing sticking out into the pool, who actually cuts everything off and levels it, installs the fittings etc. Is that the plaster company?
Sorry, sitting here trying to figure out what sub contractors I still need to finish the job. Pics below