Hello,
long time viewer, first post....
pool under construction with pool builder. Shotcrete is/was today, they are still going 5:30 in las vegas and dark. as title says they collapsed a wall as they were shotcreting. Wall in deep end, 15 feet long up to 8 feet deep.
The metal reinforcements bowed so much the had to drive spikes into ground and ratch strap them back into place. Metal still bowed out 3-4” into pool and there was at least a 6 inch “wave “ in the wall. Then they poured probably 20 gallons of water on it to help shovel away that shotcrete.
so question what now? How will this effact the integrity of the wall, the metal reinforcement and also the deep end floor which now has 20 or so extra gallons of water on its yet to be poured shotcrete.
josh
long time viewer, first post....
pool under construction with pool builder. Shotcrete is/was today, they are still going 5:30 in las vegas and dark. as title says they collapsed a wall as they were shotcreting. Wall in deep end, 15 feet long up to 8 feet deep.
The metal reinforcements bowed so much the had to drive spikes into ground and ratch strap them back into place. Metal still bowed out 3-4” into pool and there was at least a 6 inch “wave “ in the wall. Then they poured probably 20 gallons of water on it to help shovel away that shotcrete.
so question what now? How will this effact the integrity of the wall, the metal reinforcement and also the deep end floor which now has 20 or so extra gallons of water on its yet to be poured shotcrete.
josh