Update/non-update...
Still waiting on our permit from the city to come through. We were told it was 7-10 days, and today is day 9. Apparently it is with the zoning team, and they incorrectly reported that we have an internet line running where the pool will be -- the internet line runs through our front yard, so we don't know what is going on there. So very hopeful this gets resolved quickly, and we can start digging next week. Our current planned gunite date is 8/13.
We also met with a gas company yesterday about installing an underground 500lb propane tank, replacing our current 100lb above-ground one. We've talked to 3 companies, and the one from yesterday is who we'll go with. They'll tie into our existing lines (for our oven/stove, fireplace and grill outside), then run the lines to the heater and fire pit from the tank.