Longtime TFP lurker. Excited to finally have a thread to share of my own.
13 x 30
Salt water
Pentair 1.5HP 2-speed (might explore variable speed)
Pentair 150 sq ft cartridge filter
6 ft tanning ledge
Swimout facing house (can't wait for this feature)
12-ft wide deck to west of pool (Dominican Coral Stone)
Coping: Domincan Coral Stone
We broke ground late last week. Our pool will be a simple design, with minimal decking. The pool will be set somewhat far back from house, but really have had a chance over the last few years to conceptualize the sunlight.
PB forecasts a 4-6 month process based on Miami summer rains and COVID. Originally, we were at 12 weeks from permit approval. Hopefully it all goes well and we are swimming sooner rather than later.
Like my friend Ryanrichard25 (very similar design/style), we were slated to start on Memorial Day weekend. But the impossible rains (14 inches in 72 hours) pushed us back a few days. Luckily the excavation went well. It's a bigger mess than I anticipated.
Pictures to follow.
13 x 30
Salt water
Pentair 1.5HP 2-speed (might explore variable speed)
Pentair 150 sq ft cartridge filter
6 ft tanning ledge
Swimout facing house (can't wait for this feature)
12-ft wide deck to west of pool (Dominican Coral Stone)
Coping: Domincan Coral Stone
We broke ground late last week. Our pool will be a simple design, with minimal decking. The pool will be set somewhat far back from house, but really have had a chance over the last few years to conceptualize the sunlight.
PB forecasts a 4-6 month process based on Miami summer rains and COVID. Originally, we were at 12 weeks from permit approval. Hopefully it all goes well and we are swimming sooner rather than later.
Like my friend Ryanrichard25 (very similar design/style), we were slated to start on Memorial Day weekend. But the impossible rains (14 inches in 72 hours) pushed us back a few days. Luckily the excavation went well. It's a bigger mess than I anticipated.
Pictures to follow.