Frisco5, Itll be 3.5 to 5 ft deep, as any more of a slope in such a short space wouldve made the bottom very awkward to stand on. Im hoping the progress keeps up at this pace, but from watching others on here, its not likely. 
We thought that. One week in, the dig, rebar, plumbing stub of pool and gunite had all been done. How could this take any more than 4 weeks we thought...LeLori said:Frisco5, Itll be 3.5 to 5 ft deep, as any more of a slope in such a short space wouldve made the bottom very awkward to stand on. Im hoping the progress keeps up at this pace, but from watching others on here, its not likely.![]()
Frisco5 said:That is looking great... Did you figure out if the chairs would fit on the right side of the pool?
I meet with some from your PB today, I should have a design by the end of the week.