I know I'm a little late to the party as I just finished up my owner/builder build, but there are a couple things to consider on your timing.So is this order valid for using concrete coping which is contiguous with the concrete deck?
I thought the pool needed to be filled right after the plaster to help it cure without cracking?
- Get a pool design and engineering
- Get bids and select contractors
- Complete layout, dig, and steel
- Plumbing rough in
- electrical rough in
- gunnite
- Water edge tile
- finish electrical
- finish plumbing
- Plaster/pebbletec finish
- Decking and coping
- Pool fill and initial startup
If you are going with a cantilever coping (example- poured in place concrete or kooldeck), I would recommend this route
- Get a pool design and engineering
- Get Permit
- Get bids and select contractors
- Complete layout, dig
- Plumbing rough in
- Steel
- electrical rough in
- gunnite
- finish electrical
- finish plumbing
- Decking and coping
- Water edge tile
- Plaster/pebbletec finish
- Pool fill and initial startup
- Get a pool design and engineering
- Get Permit
- Get bids and select contractors
- Complete layout, dig
- Plumbing rough in
- steel
- electrical rough in
- gunnite
- finish electrical
- finish plumbing
- Water edge tile
- Coping, then decking
- Plaster/pebbletec finish
- Pool fill and initial startup