Hoping for some suggestions once this build gets started. My PB is apparently going to cheat me out of some equipment that was in the original contract October 2020 and other equipment changes that were made in January 2021. I give the dates because the supply challenges should have no bearing on my pool since everything has been known for 18 months! Anyhow, to start, PB ordered wrong slide (SRS Turbotwister) when 10/20 contract stated Typhoon. My project doesn't doesn't even allow the space for the TurboTwister

. I've already remedied the slide on my own.
Another major thing is the PB has completely ignored my plumbing diagram requests since Jan 2022 and even further back. PB ordered wrong/not enough valves, so I am working on getting that corrected on my own. Not a big problem, I can handle, but why am I GC'ing my own build when I've paid for it to all be done for me.
Biggest problem: PB has most of my equipment wrong or completely missing. Original contract had IC60. PB never even ordered one. Original contract had 1.5 hp superflo, changed 01/2021 to 3 hp IntelliFlo. PB still ordered superflo. Added IntelliConnect 01/2021, PB never ordered. Looks like there's no way I'll be able to qualify for the Pentair 3 year warranty now because I won't have 3 items on the same invoice. My other equipment is TR100 filter and UT 140 which appear to have been ordered correctly. I wouldn't wish this PB on anybody, even Voldemort.
What would be best way to set up the pool/equipment pad/plumbing, knowing changes will be made later when right equipment arrives, with this wrong equipment? There's something about "unions" or something to make equipment connections easier? Obviously, need to leave appropriate space for any missing/wrong equipment? Tapping
@Newdude @ajw22 @jimmythegreek @Dirk @Mdragger88 @Leebo