After a year of due diligence and research we finally broke ground. I'm a bit in arrears but here's the progress over the first 4 days:



6/2 - Dig Day 1

6/3 - Dig Day 2

6/4 - Steel (#5 for footing/#3 for footing "wrap-arounds), #4 everywhere else. 8" thick gunite for floor, 6" for footing, 12" for walls/bond beam.

6/6 - Stub-Outs

6/7 - Clean out/reshape trenches, floor and walls to ensure proper coverage of gunite.