I have been lurking for a while, since 2008 and taking notes as I prepare for my own pool journey here in the Tampa Bay Area. Below is my rough plan of what I want that I welcome any feedback on to see if I have been paying attention to the right things. I have not started getting on the long list for builders to come visit yet. First, I wanted to get my wants reviewed and dialed in so I can hand each of the builders this list to work from as a starting point. Second, I don’t trust 2020 and to start during hurricane season in a pandemic seemed like temping fate a little too much
. But I know in my area is currently in the 7 to 9 month waiting que. The Slap’s are a family of 4, 2 40 somethings, an 18-year-old off at college and a 10-year-old. Looking for relaxing and fun pool, no water sports or anything like that. I have been saving a little each month for the past 13 years to get to this point.
Pool Size and Shape
Roughly 15X30 about 16,800 gallons
Leaning towards a lazy L type design, I attached a refence picture I like
4 feet to 6 feet depth
No SPA, water features or bubblers
Pentair Equipment Package (Preferred)
IntelliFlo VSF 011056
Clean & Clear Plus CCP420 160301
IntelliCenter System (Load Center with i5P Personality Kit) 521905
Hayward Equipment Package
TriStar VS 950 SP32950VSP
Swim Clear Cartridge C4030
OmniPL Smart Pool and Spa Control with TCELL940 HLBPLUS4W
Jandy Equipment Package
VS FloPro 2.7 HP DV2A VSFHP270DV2A
CV Cartridge Filter CV460
Pump, Heater, & 5 Aux
AquaLink RS Pool/Spa Control System IQ904-P + AquaPure 40K PLC1400
Heater
Raypak 016033 R8450ti-E Digital Heat Pump 140,000 BTU
Lighting
3 or 4 MicroBrite Color 12V 620425 or 620426
Extra Equipment
Pentair IntellipH
Plumbing
2” SCH 40 Rigid PVC, all sweep elbows
12 inch plumbing trench with clean sand backfill
No main drains unless required by code, cannot seem to find anything in internet searches if they are required just that they must be VGB compliant if you have them. In Tampa Bay, FL.
6 returns staggered in depths to created better circulation.
2 Hayward SkimMaster Skimmer - 2 in.X2.5 in. Item # SP10712SGR
All home run plumbing to the pad.
Pentair Automatic Water Filler with FluidMaster Valve Item #: T40FDG. Auto Fill and Overflow. Not sure is local code requires a separate Plummer or not. Either way I want both.
Jandy or Pentair CPVC Never Lube Valves
Check Valve for Heater
Inline Zinc Anode
Flow Meter FV-C
Flowvis Digital FV-D
18” straight run before vertical install of SWG.
12” straight run before pump.
Unions for all equipment
Flood light over the equipment pad
Water tap at equipment pad
Water Line Tile
These are the type of ones I am leaning to. I am sure @kimkats will help in this area and maybe have other ideas in this type.
Tile Series: Martinique | NPTpool.com
Tile Series: Coral | NPTpool.com
Tile Series: Trident | NPTpool.com
Plaster
These are my top 3 I am considering
Eco Finish AquaBright Mediterranean Blue
Primera Stone Lazurite
Hydrazzo Mediterranean Blue
Deck
Stamped concreate is my preferred. Ashlar Stone or English Ashlar pattern. Leaning Grey or Dark Silver color. Pictures attached.
Robot Cleaner
DOLPHIN Nautilus CC Supreme or DOLPHIN Sigma
Pool Cage
Super Screen 17X20 Mesh, Double Door for moving stuff in and out
Alarms
Going to go with the window and door alarms
Draw Schedule as close to this preferred model as possible:
10% Contract Signing
30% After passing of rough in inspections (layout/dig/reinforcement/plumbing/electrical)
25% after completion of Deck and equipment
25% After passing of Electrical final and plumbing final
10% After passing Pool final inspection and punch List
I want to be fair but protect my interests as well, when is a good time to make sure lien releases are done? Is that something that should be done after each phase?

Pool Size and Shape
Roughly 15X30 about 16,800 gallons
Leaning towards a lazy L type design, I attached a refence picture I like
4 feet to 6 feet depth
No SPA, water features or bubblers
Pentair Equipment Package (Preferred)
IntelliFlo VSF 011056
Clean & Clear Plus CCP420 160301
IntelliCenter System (Load Center with i5P Personality Kit) 521905
Hayward Equipment Package
TriStar VS 950 SP32950VSP
Swim Clear Cartridge C4030
OmniPL Smart Pool and Spa Control with TCELL940 HLBPLUS4W
Jandy Equipment Package
VS FloPro 2.7 HP DV2A VSFHP270DV2A
CV Cartridge Filter CV460
Pump, Heater, & 5 Aux
AquaLink RS Pool/Spa Control System IQ904-P + AquaPure 40K PLC1400
Heater
Raypak 016033 R8450ti-E Digital Heat Pump 140,000 BTU
Lighting
3 or 4 MicroBrite Color 12V 620425 or 620426
Extra Equipment
Pentair IntellipH
Plumbing
2” SCH 40 Rigid PVC, all sweep elbows
12 inch plumbing trench with clean sand backfill
No main drains unless required by code, cannot seem to find anything in internet searches if they are required just that they must be VGB compliant if you have them. In Tampa Bay, FL.
6 returns staggered in depths to created better circulation.
2 Hayward SkimMaster Skimmer - 2 in.X2.5 in. Item # SP10712SGR
All home run plumbing to the pad.
Pentair Automatic Water Filler with FluidMaster Valve Item #: T40FDG. Auto Fill and Overflow. Not sure is local code requires a separate Plummer or not. Either way I want both.
Jandy or Pentair CPVC Never Lube Valves
Check Valve for Heater
Inline Zinc Anode
Flow Meter FV-C
Flowvis Digital FV-D
18” straight run before vertical install of SWG.
12” straight run before pump.
Unions for all equipment
Flood light over the equipment pad
Water tap at equipment pad
Water Line Tile
These are the type of ones I am leaning to. I am sure @kimkats will help in this area and maybe have other ideas in this type.
Tile Series: Martinique | NPTpool.com
Tile Series: Coral | NPTpool.com
Tile Series: Trident | NPTpool.com
Plaster
These are my top 3 I am considering
Eco Finish AquaBright Mediterranean Blue
Primera Stone Lazurite
Hydrazzo Mediterranean Blue
Deck
Stamped concreate is my preferred. Ashlar Stone or English Ashlar pattern. Leaning Grey or Dark Silver color. Pictures attached.
Robot Cleaner
DOLPHIN Nautilus CC Supreme or DOLPHIN Sigma
Pool Cage
Super Screen 17X20 Mesh, Double Door for moving stuff in and out
Alarms
Going to go with the window and door alarms
Draw Schedule as close to this preferred model as possible:
10% Contract Signing
30% After passing of rough in inspections (layout/dig/reinforcement/plumbing/electrical)
25% after completion of Deck and equipment
25% After passing of Electrical final and plumbing final
10% After passing Pool final inspection and punch List
I want to be fair but protect my interests as well, when is a good time to make sure lien releases are done? Is that something that should be done after each phase?