Down to the last 2 bids on a vinyl pool; here's the two payment schedules.
What do y'all think?
Bidder 1 Payment Schedule:
10% deposit
20% at Permit Approved
25% at Excavation
20% at Wall Set
20% at Coping
5% at Liner
Bidder 2 Payment Schedule-
1/2 down due at order of pool kit.
1/4 due when walls are up, plumbed and backfilled with gravel.
Final 1/4 upon completion and pool is up and running.
What do y'all think?
Bidder 1 Payment Schedule:
10% deposit
20% at Permit Approved
25% at Excavation
20% at Wall Set
20% at Coping
5% at Liner
Bidder 2 Payment Schedule-
1/2 down due at order of pool kit.
1/4 due when walls are up, plumbed and backfilled with gravel.
Final 1/4 upon completion and pool is up and running.