We are building our first pool and this is my first post to this forum. I have gained a lot of valuable insights from this forum. We are getting PebbleSheen on the inside.
Yesterday was supposed to be our plaster day, but after they started the compressor on the truck broke so they couldn't finish the job (Yeah, my luck!).
The builder says that now the unfinished plaster would need to cure for 5-7 days before they finish the plaster.
Does that sound accurate?
Would I have any future plaster related issues due to that?
Look forward to getting your insigh
ts.
We are building our first pool and this is my first post to this forum. I have gained a lot of valuable insights from this forum. We are getting PebbleSheen on the inside.
Yesterday was supposed to be our plaster day, but after they started the compressor on the truck broke so they couldn't finish the job (Yeah, my luck!).
The builder says that now the unfinished plaster would need to cure for 5-7 days before they finish the plaster.
Does that sound accurate?
Would I have any future plaster related issues due to that?
Look forward to getting your insigh