There were some errors on my part on the shed. The side of the sheds come down about 2" below the surface of the pad. I actually knew this about 3 months ago when I ordered the shed. There was only supposed to be one side door with the other one facing the deck. Problem is when I had the deck poured, I didn't account for the 2". So I couldn't put that front door because it'd hit the main deck. SOOO, we have to move it to the side. Not a giant problem, just changed the looks of things.
So the Wet Edge/Plastering guys came out Saturday to check things out. They came out yesterday (Tues) to clean up. They pumped out the rest of our Harvey flood water in the pool and cleaned everything up. Looks like they did a really good job.
They started to build the water fall wall in the back. Not too much progress, but they got it going.
Fence guys showed up as well and has started extending the fence for the doggies. This way if we had guests over, we can leave then in their own fenced in area (almost 3,900 sq ft worth) so they don't have to be cooped up in the house.
Equipment is supposed to go in today and tomorrow. I am thinking they will plaster today or tomorrow since there's no water in the pool now. That means there could be water in the pool by early next week?
PB and I decided to finish the floor last, after all the heavy work around the pool is done so we don't damage the finish. 2 more weeks? I think I've said that a few times.