I have been trying for 2 days to get through to my town to get an answer with no luck - my permit requires a "Final Engineering Inspection" and a "Dry Well Inspection Prior to back fill" - the second inspection is self explanatory - however, my question is, customarily what phase of construction of a steel wall in ground pool with concrete collar at base would the "final engineering inspection" take place?
I am assuming pool dug, walls in, concrete down, but prior to backfill. I am trying to independently confirm my pool builder's schedule