So my wife and I are planning on putting in our first pool. I'm a big fan of this site and would really appreciate any input. I called every pool company in the area, and of the few that actually are returning calls right now, I prefer the designer of these plans. We are only a family of 3 so far, but would like to have have friends over frequently (so wanted to go as big as I can currently afford). This design is 38' x 26'. He said that If I take the length to 40' then excavation would go into a higher cost bracket, so that is why it is not quite 40' long. We would like to be able to play vball in it, so that factored into the design. Also wanted it close to the porch so we can watch TV from the pool, and have the back patio double as an "outdoor kitchen."
Pricing Summary Total Price : $78,250
Project Specifications Pool/Spa Area: Up to 650sq ft
Pool Depth : Up to 5’
Pool/Spa Perimeter : Up to 100’
Pool/Spa Capacity : 18,000
Tanning Ledge: Up to 76sq ft with 1 bubbler and 1 umbrella sleeve
Deck Area: Up to 370sq ft of concrete deck with standard cool deck coating
Rock/Water Feature up to 3 tons: $3,000 - NOT INCLUDED IN PRICE
Base Project Includes
PLANNING PHASE
Pre-Construction Meeting: Customer Approved Pool Layout and General Construction Meeting with Construction Workbook and Overall Process Details
Site Protection: Silt Fence Erosion Control and Orange Safety Protection Fencing as Needed
Site Preparation: Fencing Removal (and Reset) for Access Route
Construction Blueprints: 1/8" Scale Project Blueprints with Detailed Construction Designs and Standard Engineered Construction Specifications
Local Building Permits: All Local Building Permits, Fees, and Scheduled Inspections if Required
HOA Permitting: Plan Specifications to Meet HOA Requirements as Needed, HOA Paperwork Assistance - HOA Fees Not Included
EXCAVATION PHASE
Elevations: Initial Pool Site and Project Elevations Set Based Upon Customer Approval
Demolition & Preparation: Demo and Remove Project Area Debris and General Site Grading as Needed
Excavation: Bobcat and/or Back-Hoe Dig with Hand Trimmed Vertically Excavated Walls, Includes Rock Dig and Spoils Haul Away if Required
Forming: Swimming Pool Perimeter Forms as per Design
Utility Trenching: Excavation of Trenches for Plumbing and Required Utility Lines, Includes Sand or Equivalent Protection for Piping
STEEL PHASE
General Steel Design: Minimum #4 (1/2") Steel @ 10" On Center Each Way, Throughout Pool Structure
Bond Beam Design: #4 (1/2") Steel x 4 Bars Throughout Upper Bond Beam of Pool
Steel Clearance: Minimum 3" Clearance Between Steel Cage and Excavated Pool Floor and Walls Allowing for Proper Gunite Thicknesses
Grounding: #8 Solid Copper Wire Around Entire Pool Perimeter with Minimum 4 Brass Connection Points on Steel Cage, Extended to Equipment Pad
PLUMBING PHASE
General Specifications: Schedule 40 Non-Corrosive PVC Buried from Pool to Equipment Pad to be Pressurized at 35psi throughout Project
Surface Skimmers: 2 automatic Surface Skimmers per Design
Recirculation Water Intakes: 2”Schedule 40 PVC with Minimum 2 Split Suction VGB Approved Anti-Vortex Safety Pool Main Drains
Recirculation Water Returns: 1.5" Schedule 40 PVC with Minimum 4 x Multi-Directional Filtered Water Returns to Pool
POOL SHELL PHASE
Structural Concrete: Pneumatically Applied Structural Concrete Pool Shell Hose Applied and Hand Finished and Shaped per Design
Pool Shell Thicknesses: Minimum 8" Floors, Walls, and Coves, Minimum 12" Thick Walls for Pools Above Grade, 12" Thick Bond Beam
Rebound Management: Proper Disposal and/or Haul Away of Concrete Rebound as Needed
Entry Steps: Standard Steps, Reef, or Beach Style Entry per Design
Swim Benches: Deep Water Benches per Design
ELECTRICAL PHASE
General Specifications: All Electrical Work to Meet Local Codes and Performed by a Licensed Electrician
Electrical Conduit: Main Power Run from Source to Equipment up to 100’ - Runs from Light Niche(s) to Junction Box(es) per Plan, Includes Conduit and Wiring
Electrical Hook-Up: Wiring and Hook-Up of All Required Equipment, Includes GFCI Breakers in Panel
Utilities: Built-In Freeze Protection to all Pumps - Utility Outlet at Pool Equipment Area
MASONRY & TILE PHASE
Pool Coping: Customer Choice Selection of Minimum 2" Thick Cut Limestone, Oklahoma Stone or Lueder.
Tile Preparation: Smooth Brown Coating and Water Proof Coating up to 9" Below Coping for Tile Preparation
Waterline Decorative Tile: 6" Row at Waterline with Premium Tile Selections (Hundreds of Choices, Including Stone and Traditional Tiles)
EQUIPMENT PACKAGE PHASE
Recirculation Filter Pump: Intelliflo Variable Speed Pump
Water Filtration: TA 100 Sand Filter with Glass Media
Automatic Pool Cleaner: Prowler 920 Robotic Cleaner
Underwater Pool Lighting: 4 Color Changing LED Lights
Equipment Controls: PL4 Easy Touch with Screen Logic Phone App Controller
Water Sanitation: Rainbow Inline Chlorine Tab Feeder
POOL INTERIOR FINISH PHASE
Pool Preparation: Clean-Out and Prepare Pool for Interior Finish Process, Includes Pumping of any Remaining Standing Water
Fittings: Interior Finish Color Coordinated Fittings to Include High Strength Glue and Waterproofing at Connections
Interior Pool Finish: Quartz Plaster - Color TBD
Initial Pool Fill: Begin Initial Pool Fill at Plaster Phase Completion, Water Supplied by Customer
START-UP & MAINTENANCE PHASE
Initial Start-Up: 1st Week Initial Pool Start-Up Service with Pool Chemical Treatments, Pump Priming, and Automation Programming
Maintenance & Service: 6 months of Bi-weekly Maintenance Service and Pool Chemical Treatments
Personal Maintenance Kit: Telescopic Pole, Chemical Test-Kit, Brush, Net, and Thermometer
Personal Training: Personal Instruction and Education on Equipment, Operation, and Maintenance Procedures ("Pool School")
PROJECT MANAGEMENT & SITE CLEAN-UP
Jobsite Clean-Up: Construction Access to be Graded Out with Topsoil, all Trash and Debris to be Cleaned, any Removed Fencing to be Reset - Does Not Include New Fencing
Project Management: Dedicated Project Site Manager with Multiple Levels of Communication
WARRANTIES
Equipment Package: 3-Year Manufacturer’s 100% Parts and Labor Equipment Package Warranty
Plumbing: 3-Year 100% Parts and Labor on all Plumbing
Electrical: 3-Year 100% Parts and Labor on all Electrical
Masonry: 3-Year 100% Materials and Labor on all Masonry
Tile: 3-Year 100% Materials and Labor on all Tile
Decking: 3-Year 100% Materials and Labor on all Decking
Lighting: 3-Year 100% Parts and Labor on all Lighting
Plaster Finishes: 7-Year Adhesion Warranty on all Plaster Finishes
Structural Warranty: 10-Year Limited Structural Warranty
Additional Information All Fences and Gates to be Brought to Code by Others All Landscaping and Irrigation Provided and Installed by Others All Construction Access Repair by Others
Pricing Summary Total Price : $78,250
Project Specifications Pool/Spa Area: Up to 650sq ft
Pool Depth : Up to 5’
Pool/Spa Perimeter : Up to 100’
Pool/Spa Capacity : 18,000
Tanning Ledge: Up to 76sq ft with 1 bubbler and 1 umbrella sleeve
Deck Area: Up to 370sq ft of concrete deck with standard cool deck coating
Rock/Water Feature up to 3 tons: $3,000 - NOT INCLUDED IN PRICE
Base Project Includes
PLANNING PHASE
Pre-Construction Meeting: Customer Approved Pool Layout and General Construction Meeting with Construction Workbook and Overall Process Details
Site Protection: Silt Fence Erosion Control and Orange Safety Protection Fencing as Needed
Site Preparation: Fencing Removal (and Reset) for Access Route
Construction Blueprints: 1/8" Scale Project Blueprints with Detailed Construction Designs and Standard Engineered Construction Specifications
Local Building Permits: All Local Building Permits, Fees, and Scheduled Inspections if Required
HOA Permitting: Plan Specifications to Meet HOA Requirements as Needed, HOA Paperwork Assistance - HOA Fees Not Included
EXCAVATION PHASE
Elevations: Initial Pool Site and Project Elevations Set Based Upon Customer Approval
Demolition & Preparation: Demo and Remove Project Area Debris and General Site Grading as Needed
Excavation: Bobcat and/or Back-Hoe Dig with Hand Trimmed Vertically Excavated Walls, Includes Rock Dig and Spoils Haul Away if Required
Forming: Swimming Pool Perimeter Forms as per Design
Utility Trenching: Excavation of Trenches for Plumbing and Required Utility Lines, Includes Sand or Equivalent Protection for Piping
STEEL PHASE
General Steel Design: Minimum #4 (1/2") Steel @ 10" On Center Each Way, Throughout Pool Structure
Bond Beam Design: #4 (1/2") Steel x 4 Bars Throughout Upper Bond Beam of Pool
Steel Clearance: Minimum 3" Clearance Between Steel Cage and Excavated Pool Floor and Walls Allowing for Proper Gunite Thicknesses
Grounding: #8 Solid Copper Wire Around Entire Pool Perimeter with Minimum 4 Brass Connection Points on Steel Cage, Extended to Equipment Pad
PLUMBING PHASE
General Specifications: Schedule 40 Non-Corrosive PVC Buried from Pool to Equipment Pad to be Pressurized at 35psi throughout Project
Surface Skimmers: 2 automatic Surface Skimmers per Design
Recirculation Water Intakes: 2”Schedule 40 PVC with Minimum 2 Split Suction VGB Approved Anti-Vortex Safety Pool Main Drains
Recirculation Water Returns: 1.5" Schedule 40 PVC with Minimum 4 x Multi-Directional Filtered Water Returns to Pool
POOL SHELL PHASE
Structural Concrete: Pneumatically Applied Structural Concrete Pool Shell Hose Applied and Hand Finished and Shaped per Design
Pool Shell Thicknesses: Minimum 8" Floors, Walls, and Coves, Minimum 12" Thick Walls for Pools Above Grade, 12" Thick Bond Beam
Rebound Management: Proper Disposal and/or Haul Away of Concrete Rebound as Needed
Entry Steps: Standard Steps, Reef, or Beach Style Entry per Design
Swim Benches: Deep Water Benches per Design
ELECTRICAL PHASE
General Specifications: All Electrical Work to Meet Local Codes and Performed by a Licensed Electrician
Electrical Conduit: Main Power Run from Source to Equipment up to 100’ - Runs from Light Niche(s) to Junction Box(es) per Plan, Includes Conduit and Wiring
Electrical Hook-Up: Wiring and Hook-Up of All Required Equipment, Includes GFCI Breakers in Panel
Utilities: Built-In Freeze Protection to all Pumps - Utility Outlet at Pool Equipment Area
MASONRY & TILE PHASE
Pool Coping: Customer Choice Selection of Minimum 2" Thick Cut Limestone, Oklahoma Stone or Lueder.
Tile Preparation: Smooth Brown Coating and Water Proof Coating up to 9" Below Coping for Tile Preparation
Waterline Decorative Tile: 6" Row at Waterline with Premium Tile Selections (Hundreds of Choices, Including Stone and Traditional Tiles)
EQUIPMENT PACKAGE PHASE
Recirculation Filter Pump: Intelliflo Variable Speed Pump
Water Filtration: TA 100 Sand Filter with Glass Media
Automatic Pool Cleaner: Prowler 920 Robotic Cleaner
Underwater Pool Lighting: 4 Color Changing LED Lights
Equipment Controls: PL4 Easy Touch with Screen Logic Phone App Controller
Water Sanitation: Rainbow Inline Chlorine Tab Feeder
POOL INTERIOR FINISH PHASE
Pool Preparation: Clean-Out and Prepare Pool for Interior Finish Process, Includes Pumping of any Remaining Standing Water
Fittings: Interior Finish Color Coordinated Fittings to Include High Strength Glue and Waterproofing at Connections
Interior Pool Finish: Quartz Plaster - Color TBD
Initial Pool Fill: Begin Initial Pool Fill at Plaster Phase Completion, Water Supplied by Customer
START-UP & MAINTENANCE PHASE
Initial Start-Up: 1st Week Initial Pool Start-Up Service with Pool Chemical Treatments, Pump Priming, and Automation Programming
Maintenance & Service: 6 months of Bi-weekly Maintenance Service and Pool Chemical Treatments
Personal Maintenance Kit: Telescopic Pole, Chemical Test-Kit, Brush, Net, and Thermometer
Personal Training: Personal Instruction and Education on Equipment, Operation, and Maintenance Procedures ("Pool School")
PROJECT MANAGEMENT & SITE CLEAN-UP
Jobsite Clean-Up: Construction Access to be Graded Out with Topsoil, all Trash and Debris to be Cleaned, any Removed Fencing to be Reset - Does Not Include New Fencing
Project Management: Dedicated Project Site Manager with Multiple Levels of Communication
WARRANTIES
Equipment Package: 3-Year Manufacturer’s 100% Parts and Labor Equipment Package Warranty
Plumbing: 3-Year 100% Parts and Labor on all Plumbing
Electrical: 3-Year 100% Parts and Labor on all Electrical
Masonry: 3-Year 100% Materials and Labor on all Masonry
Tile: 3-Year 100% Materials and Labor on all Tile
Decking: 3-Year 100% Materials and Labor on all Decking
Lighting: 3-Year 100% Parts and Labor on all Lighting
Plaster Finishes: 7-Year Adhesion Warranty on all Plaster Finishes
Structural Warranty: 10-Year Limited Structural Warranty
Additional Information All Fences and Gates to be Brought to Code by Others All Landscaping and Irrigation Provided and Installed by Others All Construction Access Repair by Others