Dallas (Southlake) Area New Build - July 2022 - Construction Thread

Just some progress pics as of Dec 1

Feature waterfall wall in progress.
Seat wall in front of front overflow basin in progress.
Waterline tile and spa tile in process (this is a very slow process). Tile is Mosa Terra Tones 2 x 24.
Cabana framing started.
Sport court grading beginning.ED810AF8-3DBA-456C-9CC8-961180AF9380.jpeg824011F3-73C0-4262-BBA8-2A0B5FD211C3.jpeg508FABE2-5D27-4FBD-83A1-27223E320D40.jpeg9AC55C44-828B-4965-82EA-EC53650BA323.jpeg49378BF9-5F1F-4A20-9761-BFA8451D7DE3.jpeg05DD389B-C474-4CB2-A1D6-FB44822AB94A.jpegEA0F2873-CA08-4320-959A-415B4C0C0BB8.jpeg
 
Last edited:
  • Like
Reactions: Newdude
Dec 16 progress pics - tile and cabana structure, footers for basin cap and hard scape, begin fire pit and bench pre construction.
 

Attachments

  • 06706517-0492-4406-8BBE-D408ED5EF3A9.jpeg
    06706517-0492-4406-8BBE-D408ED5EF3A9.jpeg
    586.4 KB · Views: 81
  • 4CB7CAE9-3E88-4E24-8736-7140AB5D929C.jpeg
    4CB7CAE9-3E88-4E24-8736-7140AB5D929C.jpeg
    507.5 KB · Views: 79
  • 5574087B-F65E-43E0-AC01-B1F20713226C.jpeg
    5574087B-F65E-43E0-AC01-B1F20713226C.jpeg
    548.5 KB · Views: 75
  • B69EB921-5D06-407C-A4EA-FF5109448F46.jpeg
    B69EB921-5D06-407C-A4EA-FF5109448F46.jpeg
    548.2 KB · Views: 77
  • 600567DC-4A7E-41AE-964A-B82DB7DDAC74.jpeg
    600567DC-4A7E-41AE-964A-B82DB7DDAC74.jpeg
    702.9 KB · Views: 75
  • 9314881A-2137-4AF7-8718-082E4B4E5797.jpeg
    9314881A-2137-4AF7-8718-082E4B4E5797.jpeg
    582.3 KB · Views: 78
  • 06092717-6D6C-4AF6-85D3-76127F50D895.jpeg
    06092717-6D6C-4AF6-85D3-76127F50D895.jpeg
    667.2 KB · Views: 80
  • 3C7B18F6-51AD-4F38-8CDD-73D7E591C895.jpeg
    3C7B18F6-51AD-4F38-8CDD-73D7E591C895.jpeg
    657 KB · Views: 80
January 12 2023 update

Deck framing and gravel done
Drainage done and tied in
Surge basin concrete cap done
Footers poured
Retaining wall excavation started
Sport court (47ft x 27ft) excavation underway - rebar is next

6A59F369-3C2E-457B-8430-0480C793FA21.jpeg
 

Attachments

  • 2EBFF930-D937-497A-A39C-E294B917210E.jpeg
    2EBFF930-D937-497A-A39C-E294B917210E.jpeg
    561.6 KB · Views: 52
  • 2E2A5CCF-5B7B-4A2A-8F0A-CB889F93614A.jpeg
    2E2A5CCF-5B7B-4A2A-8F0A-CB889F93614A.jpeg
    530.7 KB · Views: 52
  • 7FB7BCFC-CFCD-411A-959F-D26BC9AD95AC.jpeg
    7FB7BCFC-CFCD-411A-959F-D26BC9AD95AC.jpeg
    637 KB · Views: 49
  • FF86026E-2EB9-4DFA-AC42-A5449675738A.jpeg
    FF86026E-2EB9-4DFA-AC42-A5449675738A.jpeg
    612.3 KB · Views: 49
  • A29A4338-B562-49B1-96DC-DCB33E979D97.jpeg
    A29A4338-B562-49B1-96DC-DCB33E979D97.jpeg
    565.5 KB · Views: 50
  • AAD0C208-89AA-4A77-A6CE-7E3C561A14CC.jpeg
    AAD0C208-89AA-4A77-A6CE-7E3C561A14CC.jpeg
    676.1 KB · Views: 50
  • 0303645E-7BA0-42AA-8B64-9308E4BA5C28.jpeg
    0303645E-7BA0-42AA-8B64-9308E4BA5C28.jpeg
    375.5 KB · Views: 49
Last edited:
  • Like
Reactions: Bijju and Newdude
9C25BF8C-C056-4524-BBA0-4E2C361EF0C7.jpegCDD5CD60-10A0-4D14-9F9A-B3B59E4A55FE.jpeg4020829F-F16C-4709-9FE0-099BD26EE3CD.jpegA23AEDE7-821B-4C71-BD3E-F5EFFA26249F.jpegJanuary 18 2023 update
- seat wall built and stone capped
- pool wall stone capped
- pool tile continues
- deck in progress and steps framed
- footer wall and cast stone capped for landscape
- fire pit in progress
- retaining wall footers in progress
- sport court rebar done
 

Attachments

  • E07CD2D5-70D3-4328-93E4-41F792787116.jpeg
    E07CD2D5-70D3-4328-93E4-41F792787116.jpeg
    566.5 KB · Views: 19
Feb 2023 progress.

Lost two weeks due to weather

Sport court slab done
Rear retaining wall done
Rear steps roughed out in CMU
Pool planters roughed out in CMU
Surge Basin tile complete
Feature wall, planters and retaining all all waterproofed
Rough rear grading done
 

Attachments

  • EB109FB4-8D6D-46FB-8E97-203FB56ECD3F.jpeg
    EB109FB4-8D6D-46FB-8E97-203FB56ECD3F.jpeg
    476.2 KB · Views: 57
  • A7C7C5F9-919F-4AE7-A82E-279CD90414F0.jpeg
    A7C7C5F9-919F-4AE7-A82E-279CD90414F0.jpeg
    528.5 KB · Views: 59
  • 6F2D7442-6643-4BC6-A751-4864DEB528F4.jpeg
    6F2D7442-6643-4BC6-A751-4864DEB528F4.jpeg
    446 KB · Views: 60
  • 100C4B99-B724-4B5A-AE6E-FE2FFE51B7B4.jpeg
    100C4B99-B724-4B5A-AE6E-FE2FFE51B7B4.jpeg
    782.3 KB · Views: 60
  • 6BE1A8DA-95D0-4148-B2B1-640CD3B2A7F2.jpeg
    6BE1A8DA-95D0-4148-B2B1-640CD3B2A7F2.jpeg
    574.6 KB · Views: 59
  • 4D3B3F7F-21CF-4702-B9DF-721B27D1A7F2.jpeg
    4D3B3F7F-21CF-4702-B9DF-721B27D1A7F2.jpeg
    518.1 KB · Views: 58
  • 672C2999-C604-4902-AF7E-77498DDD1780.jpeg
    672C2999-C604-4902-AF7E-77498DDD1780.jpeg
    648.7 KB · Views: 58
April 10, 2023 update.

Grading, and more grading.
Concrete pads formed up
Rear steps roughed out
Cabana step downs roughed in
Infratech WD60 heaters and flush mounts boxed in (2 in cabana, 4 in existing patio)
Existing patio demoed for new tongue and groove ceiling.
Cabana cabinets roughed in
Various tile work continues
 

Attachments

  • 324A32C4-1543-42FC-AA91-A7C39943BD13.jpeg
    324A32C4-1543-42FC-AA91-A7C39943BD13.jpeg
    549.3 KB · Views: 62
  • C15FCB23-D8FC-4EB3-8191-5ABDAC533E73.jpeg
    C15FCB23-D8FC-4EB3-8191-5ABDAC533E73.jpeg
    431.9 KB · Views: 59
  • D500014E-F563-4D9E-AC69-26840CCD0A1C.jpeg
    D500014E-F563-4D9E-AC69-26840CCD0A1C.jpeg
    596.8 KB · Views: 60
  • 0FA66DAD-ACB9-48A8-9AC3-7B1854EA5122.jpeg
    0FA66DAD-ACB9-48A8-9AC3-7B1854EA5122.jpeg
    528.5 KB · Views: 61
  • A0856B99-CBBE-4889-82A3-FB96A21ADE5D.jpeg
    A0856B99-CBBE-4889-82A3-FB96A21ADE5D.jpeg
    560.7 KB · Views: 63
  • 288D3EAD-C18F-4E3E-B9A0-55E2EEF6519A.jpeg
    288D3EAD-C18F-4E3E-B9A0-55E2EEF6519A.jpeg
    617.5 KB · Views: 60
Last edited:

Enjoying this content?

Support TFP with a donation.

Give Support
Are you gonna get in by end of summer? Or will you have to wait a whole nother year.
Pool company said eight more weeks almost four weeks ago. I give them some slack though as I want it done right and some stuff like the tile, engineering inspections etc took way longer than anyone could have reasonably anticipated. Or so they convinced me…

If we could get trades to show up on consecutive days, we could probably be done sooner - ha.
 
  • Like
Reactions: RickRude
Eventually, I am told, the pads will be acid washed to even out the color powder and streaking, but probably not until closer to the end of the project. I don’t have any real experience with that process, so we will see.
 