Dallas Pool Build

Casey

TFP Expert
LifeTime Supporter
Apr 16, 2007
11,814
SW PA
Pool Size
17000
Surface
Fiberglass
Chlorine
Salt Water Generator
SWG Type
Jandy Aquapure 1400
Things have come to a complete stop on our pool, there is an equipment shortage... he has not ETA on it, and some suppliers are saying its a 2 month wait... I am really hopeful that turns around quickly... if anyone has a suggestion on a way to get it quicker, please share :)

Thanks
Unfortunately, with that major freeze in Texas, everyone else (including you) wants new equipment too. You may just have to wait... aka... get in line.

Covid put a huge strain on the pool industry last year. Then that big freeze in Texas was just a slap in the face on top of it.
 

jbctech

Member
Oct 31, 2020
6
Frisco, TX
Pool Size
11500
Surface
Plaster
Chlorine
Liquid Chlorine
Things have come to a complete stop on our pool, there is an equipment shortage... he has not ETA on it, and some suppliers are saying its a 2 month wait... I am really hopeful that turns around quickly... if anyone has a suggestion on a way to get it quicker, please share :)

Thanks
We are also waiting on equipment and our PB said that it's on order. They haven't said it would be 2 months though. I definitely hope it's not that long! We have everything done up to Tile and Coping but they can't do electrical without the equipment being in, so we're just waiting...
 

wreckem

Active member
Mar 3, 2021
37
Texas
Pool Size
18000
Surface
Plaster
Chlorine
Salt Water Generator
SWG Type
Pentair Intellichlor IC-40
My PB ordered my equipment the day they dug in early Feb. Thankfully that was before the winter storm so they haven my equipment and have installed some of it. Unfortunately we are waiting on labor to free up for tile and coping to get installed. I still hope everything will be complete by Memorial Day. Everything is all backlogged, materials, labor, etc.
 

Dallaspoolneed

Well-known member
Feb 9, 2021
56
Dallas texas
My PB ordered my equipment the day they dug in early Feb. Thankfully that was before the winter storm so they haven my equipment and have installed some of it. Unfortunately we are waiting on labor to free up for tile and coping to get installed. I still hope everything will be complete by Memorial Day. Everything is all backlogged, materials, labor, etc.
My PB took a deposit (I think 6-7K) and during the wait we suggested that we may not want to build due to the delays and he told us that he had already "gotten" the equipment clearly that was not the case.

I am ready to be done with this thing, I am wondering when we can ask to put the yard back together, the plumbing is now complete I wonder if they can just turn on the sprinklers so we can get ahead of the texas heat.
 

Dallaspoolneed

Well-known member
Feb 9, 2021
56
Dallas texas
Electrician question,

The electrician wants to run the wire for the pool through the attic, so there will be an exterior PVC pipe coming down the side of the house (2 locations) and then he will trench to the location where the equipment is... Seems to me like this is a "short cut" or a way to save time or money.

Anyone have any advice on this?
 

ajw22

Gold Supporter
TFP Guide
Jul 21, 2013
23,578
Northern NJ
Pool Size
35000
Surface
Plaster
Chlorine
Salt Water Generator
SWG Type
Pentair Intellichlor IC-60
Running through the attic is not a problem as long as you are fine with some pipes running down the side of the house. He needs to do it to code with the proper wires and PVC,

 

wreckem

Active member
Mar 3, 2021
37
Texas
Pool Size
18000
Surface
Plaster
Chlorine
Salt Water Generator
SWG Type
Pentair Intellichlor IC-40
You are going to most likely have a pipe/conduit on the side of the house no matter how they do it. My equipment pad is near my meter and the breaker box. They punched a hole right next to the meter and ran another conduit pipe. Then trenched.

I am assuming your equipment pad is on the opposite side of the house as the breaker box. That’s the only reason I could see them wanting to use the attic.
 

GDN

Bronze Supporter
Oct 17, 2016
474
Dallas, TX
If it wasn't specified up front and they are just trying to avoid the trenching then stick to your guns. They will cut every corner, but you will look at it and see it every day.
 

Dallaspoolneed

Well-known member
Feb 9, 2021
56
Dallas texas
If it wasn't specified up front and they are just trying to avoid the trenching then stick to your guns. They will cut every corner, but you will look at it and see it every day.
Seems like this was the goal for them, they still trenched about 50 ft vs 80 ft to avoid the attic run. I am glad we did it this way.

Thanks everyone for their advice.
 

Enjoying this content?

Support TFP with a donation.

Give Support

Dallaspoolneed

Well-known member
Feb 9, 2021
56
Dallas texas
So we were supposed to have 2 lights in our pool (two on the long wall facing in the same direction) and it seems during the build they only planned for one light (in the center of the long wall)

it seems during the electrical rough in they have placed a line in the middle of the short wall this means

1. They will drill through the gunite for the second light which I don’t know anything about.
2. How will that look ?

any input is greatly appreciated.