*UPDATE: As suggested from the wise folks on this forum - the flashing was a thin layer of Gunite to protect the dig from the weather. But my construction is now on hold because the PB says the spa jets are on backorder. I was told there is a national shortage - so we are patiently waiting on parts to continue.
So excavatoon happened a few days ago and I thought that the placing of rebar was the next step (from watching you tube videos). But today a Gunite truck showed up. When I asked about the rebar I was told that the Gunite can go down first and that they intended to “flash” it. Is this true? I called my PB and he said that the crew needed to wait for the metal crew. When I got off the phone however - they had already “flashed“ it with Gunite. Is this a problem or concern?
So excavatoon happened a few days ago and I thought that the placing of rebar was the next step (from watching you tube videos). But today a Gunite truck showed up. When I asked about the rebar I was told that the Gunite can go down first and that they intended to “flash” it. Is this true? I called my PB and he said that the crew needed to wait for the metal crew. When I got off the phone however - they had already “flashed“ it with Gunite. Is this a problem or concern?
Last edited: