Small one depth 12'x26'x4'6" rectangular fiberglass pool from Dolphin Fiberglass Pools - Stingray III Caribbean Blue
Being built by York Region Hot Tub and Pools - planned completion date before Canada Day July 1st
Here's my 2018 Design to start with:
Main patio - 36'x15'
Natural stone coping 1'x6'
Surround pool deck - 4'
Planned equipment - Everything Pentair
- Variable 3HP pump
- IC20
- Cartridge filter - 320 inch
- Heater - 250k
- 2 pentair led glowbrite
- automation with wireless

I'll post some pictures of progress as soon as I get them off my gopro - stay tuned
Videos:
Here's a run down of the days when crew was working - mostly a few hours per day:
Day 1 - The Dig
Day 3/4 - Set up
Day 5 - Pool install
Day 6 - Backfill - Lost footage, doh!
Day 7 - Slight uh-oh
Day 8 - Level steps section
Day 9 - Cement Collar, Equipment Pad and Lighting
Day 10 - Coping & Pavers delivery - nothing exciting to capture
Day 11 - Prepping area for paver work - nothing exciting to capture
Day 12 - Coping
Day 13 - Setting the pavers base - nothing exciting to capture
Day 14 - Electrical work
Day 15 - Main patio and pool wash
Day 16 - Finish laying all pavers
Day 17 - Finishing pavers with Polymeric sand
Day 18 - Pea Gravel and Preparing base for sod
At some point in time - I'd like to end up with something like this - 2019 or 2020

Enjoy
David
Being built by York Region Hot Tub and Pools - planned completion date before Canada Day July 1st
Here's my 2018 Design to start with:
Main patio - 36'x15'
Natural stone coping 1'x6'
Surround pool deck - 4'
Planned equipment - Everything Pentair
- Variable 3HP pump
- IC20
- Cartridge filter - 320 inch
- Heater - 250k
- 2 pentair led glowbrite
- automation with wireless

I'll post some pictures of progress as soon as I get them off my gopro - stay tuned
Videos:
Here's a run down of the days when crew was working - mostly a few hours per day:
Day 1 - The Dig
Day 3/4 - Set up
Day 5 - Pool install
Day 6 - Backfill - Lost footage, doh!
Day 7 - Slight uh-oh
Day 8 - Level steps section
Day 9 - Cement Collar, Equipment Pad and Lighting
Day 10 - Coping & Pavers delivery - nothing exciting to capture
Day 11 - Prepping area for paver work - nothing exciting to capture
Day 12 - Coping
Day 13 - Setting the pavers base - nothing exciting to capture
Day 14 - Electrical work
Day 15 - Main patio and pool wash
Day 16 - Finish laying all pavers
Day 17 - Finishing pavers with Polymeric sand
Day 18 - Pea Gravel and Preparing base for sod
At some point in time - I'd like to end up with something like this - 2019 or 2020

Enjoy
David