I posted a prior thread about this issue, but I had all the facts wrong, so rather than correct it in that thread I decided to post a new thread with detailed pictures. After my pool passed the bonding inspection (in which there was a copper wire around the perimeter of the pool and also a copper wire connected to all the equipment on the pad), my contractor came in to build a grotto and a slide. The slide was bonded together to the copper wire that was going around the perimeter of the pool and that bonding will be inspected Tuesday. To give you a perspective, below is a picture of the Grotto (which doesn't have its roof on yet) when standing near my house.
The contractor dug behind the Grotto three feet down and poured footings for the slide as well. Below are pictures of what it looked like after they dug.
The pictures below show the area behind the Grotto he dug up, and in the one picture below showing both the pipes and the footings, you can see that the contractor laid down two pieces of REBAR that ran around the perimter behind the Grotto. You can see if you look closely that he tied those two pieces of REBAR together to a piece of REBAR that was coming out of the Pool. It seems to me that since all the REBAR in the Pool was bonded, the tying the new REBAR to the Pool REBAR is sufficient to bond this new REBAR. However, after he poured in some concrete, he apparenbtly put two more pieces of REBAR into the area behind the Grotto and then poured mor concrete. I don't have any pictures of this and did not see him do it, but he told me he did. My question is: What if when he put the other REBAR into this area, he did not tie it to any of the Pool's REBAR. Now I would have REBAR in concrete that is 16 inches from the water's edge. No one exiting the Pool would stand directly on the ground where that untied in REBAR is, but when in the Grotto, you do touch the walls of the Grotto when you lean back and those walls are somewhat over the ground where that untied in REBAR is. In addition, when you walk to go on the Slide (steps and pathway not done yet), you are walking a little (although not directly) over the ground where that REBAR would be. Now the contractor actually doing the work doesn't speak English very well so I don't know if he tied in that additional REBAR, and will try to have someone ask him for me on Tuesday. My question is assuming he did not, do we have a serious issue?
The contractor dug behind the Grotto three feet down and poured footings for the slide as well. Below are pictures of what it looked like after they dug.