PebbleTec being applied next week and forecast is windy - problem?

lvrpl

0
LifeTime Supporter
Jun 18, 2015
159
Connecticut
We’ve got a new build that’s finally getting the plastering done next week. We’re going with Pebble Sheen. We’re building a 26k inground pool and our pool builder says it will be a two day process - pebble sheen applied the first day, then acid wash the second day (and then filled with water the second day, in the afternoon).

Our forecast is showing wind both of those days - 10-20 mph generally. Is it problematic to do the final finish application while there is wind? Should I be concerned?

Thanks for any help.
 
The application is a slow sludge being applied, so wind does not affect it staying in place. The wind issue is more of a concern if there is debris blowing from trees, etc. Some times a PB will put up a barrier but that is subjective.
Info for your big day
Day of Plaster

  • Clean up around the pool area the day before - brush any dirt/mud or debris that could be tracked into the pool during or after plaster
  • Verify that the bags of plaster are the proper type and color you selected on morning of plaster.
  • Take a sample of the mixture when they are applying it to the pool by pouring some in a small clear plastic cup (good for reference later)
  • Do they have all the proper return nozzles and drain covers (type and color) to place after plaster installed
  • Have you tested your fill water? Are you filling with softened water or regular tap water or well water?
  • Have your hose ready (and clean) as it will be laying in the pool.
  • Tie a sock or cloth around the nozzle so it does not sit on the plaster or place a pool noodle over the hose end. See more below.
  • Put the end of the hose at the lowest part of the pool to avoid channeling in the new plaster. Also, consider tying a plastic jug to the nozzle such that it will float up as the water rises. Or another method is to take two pool noodles and threaded the hoses through the middle of the noodles which will keep the hose suspended on the water surface and away from the pool walls.
  • Ensure you take note (or a picture) of your water meter reading before you start to fill
  • Be prepared to take note of your water meter as the pool reaches certain levels, i.e bottom of bottom step, top of bottom step, etc. (it helps in the future to know volume of your pool at certain levels - should you ever have to drain portion of it)
  • Plan to set an alarm every 4 hours (or so) to ensure hose is still in pool, no debris blew into pool, etc.
  • Do NOT stop the flow of water once the pool starts filling as doing so could cause a ring on the new plaster.
  • Take a picture of any chemicals they bring on site that they plan to dump in when they start to add water to pool
  • Continue to fill pool to center of water tile or center of skimmer. Take picture of water meter at end of fill
  • Get clear instructions from PB as what to do the day the pool is full - how often to brush, will the pump be turned on, etc.
  • Define with PB when he will be back out to set up water chemistry.
 
  • Like
Reactions: lvrpl
@HermanTX shared his great steps for getting new plaster! Read them one at a time. I would even suggest you print them out and checking off each item to make sure it is done. Each step is very important.

Let us know what the PB says about the after care of your plaster as that is also a very important step.
 
  • Like
Reactions: lvrpl
The application is a slow sludge being applied, so wind does not affect it staying in place. The wind issue is more of a concern if there is debris blowing from trees, etc. Some times a PB will put up a barrier but that is subjective.
Info for your big day
Day of Plaster

  • Clean up around the pool area the day before - brush any dirt/mud or debris that could be tracked into the pool during or after plaster
  • Verify that the bags of plaster are the proper type and color you selected on morning of plaster.
  • Take a sample of the mixture when they are applying it to the pool by pouring some in a small clear plastic cup (good for reference later)
  • Do they have all the proper return nozzles and drain covers (type and color) to place after plaster installed
  • Have you tested your fill water? Are you filling with softened water or regular tap water or well water?
  • Have your hose ready (and clean) as it will be laying in the pool.
  • Tie a sock or cloth around the nozzle so it does not sit on the plaster or place a pool noodle over the hose end. See more below.
  • Put the end of the hose at the lowest part of the pool to avoid channeling in the new plaster. Also, consider tying a plastic jug to the nozzle such that it will float up as the water rises. Or another method is to take two pool noodles and threaded the hoses through the middle of the noodles which will keep the hose suspended on the water surface and away from the pool walls.
  • Ensure you take note (or a picture) of your water meter reading before you start to fill
  • Be prepared to take note of your water meter as the pool reaches certain levels, i.e bottom of bottom step, top of bottom step, etc. (it helps in the future to know volume of your pool at certain levels - should you ever have to drain portion of it)
  • Plan to set an alarm every 4 hours (or so) to ensure hose is still in pool, no debris blew into pool, etc.
  • Do NOT stop the flow of water once the pool starts filling as doing so could cause a ring on the new plaster.
  • Take a picture of any chemicals they bring on site that they plan to dump in when they start to add water to pool
  • Continue to fill pool to center of water tile or center of skimmer. Take picture of water meter at end of fill
  • Get clear instructions from PB as what to do the day the pool is full - how often to brush, will the pump be turned on, etc.
  • Define with PB when he will be back out to set up water chemistry.
I added your checklist with a few edits to Plaster Installation and Maintenance - Further Reading
 
  • Like
Reactions: HermanTX