Framing for our deck begins Saturday! The waterfall/slide and tile has taken 4 weeks. They have worked on it 6 days a week for 4 weeks. I never realized how slow of a process this is. But we are being patient. The problem is they have 3 guys but only one actually lays the tile and coping. So, they get about 10 pieces of flagstone down a day. 😫 Thanks for letting me vent!! Lol... ALMOST. THERE.
 