TimeLine
Early June 2021 Started contacting pool builders and reviewing proposals
July 17th 2021 - Signed Contract with PB2 (See quote below) Contract Signed!
July 20th 2021 - Downloaded and learned to use Pool Studio
September 23rd 2021 - County and City Permits approved
November 22nd 2021 - Excavation has begun!
November 29th - Plumbing
December 2nd 2021 - Steel
December 6th 2021 - Gunite applied!
December 8th 2021 - Tile Installed
December 16th 2021 - Electric Installed
December 22nd 2021 - Water Feature and coping installed
January 25th 2022 - Deck Forms laid out
February 11th 2022 - Deck poured and concrete stamped
February 28th 2022 - Fence Installed!
March 25th 2022 - Plaster applied
March 28th 2022 - POOL COMPLETED!!!!!
Time Lapse Video of Build
Hello everyone, my wife and I are very close to pulling the trigger on a new pool here in the Dallas / Fort Worth area. This forum has been an invaluable source of information, and so glad I found it when I did as we have zero experience with pools and this will be our first! We have talked with 4 different pool builders in the DFW area, and have narrowed the selection down to two different builders. I would love to get the forums feedback in the two quotes we are considering. Thanks all!!
PB 1 (Pool Builder 1)
Basics:
Decking:
Payment Schedule:
=======================================================================================================================
PB 2 (Pool Builder 2 ***WE SELECTED THIS BUILDER****)
Basics
Decking:
Payment Schedule:
Early June 2021 Started contacting pool builders and reviewing proposals
July 17th 2021 - Signed Contract with PB2 (See quote below) Contract Signed!
July 20th 2021 - Downloaded and learned to use Pool Studio
September 23rd 2021 - County and City Permits approved
November 22nd 2021 - Excavation has begun!
November 29th - Plumbing
December 2nd 2021 - Steel
December 6th 2021 - Gunite applied!
December 8th 2021 - Tile Installed
December 16th 2021 - Electric Installed
December 22nd 2021 - Water Feature and coping installed
January 25th 2022 - Deck Forms laid out
February 11th 2022 - Deck poured and concrete stamped
February 28th 2022 - Fence Installed!
March 25th 2022 - Plaster applied
March 28th 2022 - POOL COMPLETED!!!!!
Time Lapse Video of Build
Hello everyone, my wife and I are very close to pulling the trigger on a new pool here in the Dallas / Fort Worth area. This forum has been an invaluable source of information, and so glad I found it when I did as we have zero experience with pools and this will be our first! We have talked with 4 different pool builders in the DFW area, and have narrowed the selection down to two different builders. I would love to get the forums feedback in the two quotes we are considering. Thanks all!!
PB 1 (Pool Builder 1)
Basics:
- 35'x17' geometric pool, tanning ledge, Wall with three 2' sheer descent, 3.5' shallow, sloped to 6' in deepend 120' perimeter, 676 sf, 24,082 gallons
- HotTub/SPA: 38 sq Ft, 6 jets, Master temp 400 Heater, 1 LED
- Soil Prep: Not recommending soil injections based off of experience in area.
- Structure: 4 bar box 1/2", Steel , 3/8 steel on walls and flow 10” inch centers, no documentation on thickness
- Plumbing: PVC Routed around the Pool, No heat bending, 2 drains, 2 skimmers, 4 returns,
- Plaster: Pebble
- Lights: 3x Globrite color LED lights
- Equipment: Pentair Cartridge filter 520, Pentair SVRS Pump, Superflo 2hp booster pump, EZ Touch 8 with Salt
- Sanitation: Intellichlor Salt Chlorine generator
- Pool Cleaner: Pentair Racer Cleaner
- ~1085 sf salt texture
Payment Schedule:
- Down payment - 500
- Due at start of Excavation - 35%
- Due at start of Gunite - 30%
- Due at start of coping - 30%
- Due at start of Plaster - 5%
- 3 year Pentair Equipment
- 10 year Structure
- Unclear on other warranties based on paperwork we have
PB 2 (Pool Builder 2 ***WE SELECTED THIS BUILDER****)
Basics
- 35'x17' geometric pool, tanning ledge, Wall with three 2' sheer descent, 3.5' shallow, sloped to 6' in deepend 120' perimeter, 676 sf, 24,082 gallons
- Hottub/SPA: 56 sq Ft, 8 jets, Jandy JXi 4000 Heater, 1 LED. Looped plumbing to balance jet performance. VGB main drain for plumbing.
- Soil Prep: Soil Injections Included under pool and decking. fill gravel to separate plumbing from gunnite and to keep water from ponding under pool structure
- Plumbing: PVC Routed 24" under the Pool, uses heat bending, 2 drains, 2 skimmers, 5 returns,
- Structure: 5 bar box 1/2", Steel 10” centers. 8”-10” inch thick floors and walls
- Plaster: Pebble
- Lights: 3x Spectrun360 color LED lights, 1 LED in tanning ledge bubbler
- Equipment: Jandy 2.7HP circulation pump, Jandy 2.0 HP booster, 580 Jandy Cartridge Filter, Jandy PDA PS6 controller, Auqualink IQ20A
- Sanitation: Jandy Aqua Pure Salt System PLC1400C
- Cleaner: MayTronics Dolphin M600
- ~1085 sf salt texture
- Down payment - 1000
- Due at start of Excavation - 35%
- Due at start of Gunite - 30%
- Due at start of coping - 30%
- Due at start of Plaster - 5%
- 3 year Jandy Equipment
- Lifetime Structure
- 1 year workmanship