Getting ready to put in fixtures in to rebar.. (skimmers, main drain)... In the engineered plans the main drain calls for a 4" tunk.. The plans also spec out two main drains called
" Lawson aquatic 9 super-sump vgb certified" anyway the port where is connects is a 4" connection but not open. It is sealed with only looks like a 1/2 treaded hole with a cap screwed in....... My question is, do i cut the 4" hole open before gluing on? Why a 4" line when the feed hole is only 1/2".. any help would be great,
" Lawson aquatic 9 super-sump vgb certified" anyway the port where is connects is a 4" connection but not open. It is sealed with only looks like a 1/2 treaded hole with a cap screwed in....... My question is, do i cut the 4" hole open before gluing on? Why a 4" line when the feed hole is only 1/2".. any help would be great,