We will soon have a 21' above ground installed and I want to be sure the plumbing plan I have is good.
I bought 6 of these for $50 shipped to use throughout since they are a on/off valve plus union http://www.amazon.com/89653-Precision-Threaded-Female-Socket/dp/B0032JSQ6G
My pump and filter is 1-1/5 HP 22" sand filter 520-1700 22″ Sand Filter – 1.5 HP Center Discharge Pump 2.5 sq. ft. 50 GPM 24,000 – 30,000 150 3 ft. NEMA
We also will use a Chlorinator http://www.sunplay.com/king-technology-perform-max-920-01-05-0920
The equipment will be 5-6 feet from the pool on a small slab I will pour and my electrician will run a dedicated GFCI plug to the site.
Will 1/1/2" SCH 40 hard PVC be large enough
I want them under ground to keep the area around the pool neat.
I bought 6 of these for $50 shipped to use throughout since they are a on/off valve plus union http://www.amazon.com/89653-Precision-Threaded-Female-Socket/dp/B0032JSQ6G
My pump and filter is 1-1/5 HP 22" sand filter 520-1700 22″ Sand Filter – 1.5 HP Center Discharge Pump 2.5 sq. ft. 50 GPM 24,000 – 30,000 150 3 ft. NEMA
We also will use a Chlorinator http://www.sunplay.com/king-technology-perform-max-920-01-05-0920
The equipment will be 5-6 feet from the pool on a small slab I will pour and my electrician will run a dedicated GFCI plug to the site.
Will 1/1/2" SCH 40 hard PVC be large enough
I want them under ground to keep the area around the pool neat.