In my never ending pool project the builder states he wants to do the deck before plaster. I think the deck should be done last, but I have not worked in construction in several years has something changed.
I had to have the deck poured first for inspection purposes. That being said, I'm glad it is this order. The deck pour (as with any concrete job) has a certain 'mess' aspect to it. I'd rather have them cleaning the excess concrete off the shotcrete than the new plaster. They were physically "in" the pool to correctly place and concrete the cantilever forms, and again, I'd rather have an entire crew of workers walking around the shotcrete floor than potentially scuffing the plaster.
I agree it is messy, but sundek is a concert topping the deck has been in for two weeks..You would think he wouldn't want the pebble people running across the deck with equipment and spikes
This is what my PB said. He did the concrete pour prior to plaster and then the stamped overlay after plaster.I agree it is messy, but sundek is a concert topping the deck has been in for two weeks..You would think he wouldn't want the pebble people running across the deck with equipment and spikes