My pool builder dug the hole on april 23. The coping and tile have been completed and the plumbing went in two weeks ago. We are now 10 days beyond contract completion date of 50 days. We contracted at the the end of January and were given a verbal promise of June 1st. Here it is June 21 and we still have pavers, fencing, plaster, equipment to go in. The pool builder keeps promising dates but never meets up to them. Instead, he says that his guys have been working 7 days a week. We have not benefitted from this particularly since the concrete was poured around 5/10. Do you have any suggestions on what might motivate the pool builder? The contract calls for substantial completion within 50 days and my pool is nowhere near substantially completed and we are now 11 days beyond the due date. It is very frustrating. He will likely come through but we are apparently a very low priority. Had I predicted this then we would have waited until the fall when deals are better and gone with a different pool builder.