Self-drawn plan / design:
Day 1: Excavation. Weather is calling for thunderstorms so not sure if they will be done today or get stopped due to rain.
- 16 ft wide x 34 ft long Humpback Kidney Shape
14 Gauge “Galvanized” Steel Walls
Double track “Snap Lock” Coping
Separate Main Drain and Skimmer Suction Lines
Widemouth “Through The Wall Mount” Skimmer
Main Drain w/ Hydrostatic Valve and an “Anti-Vortex” Safety Cover
Return “Inlet” Fittings (2 in Total)
Acrylic In-Wall 8 ft Step with 2 Return Jets on a Separate Line
Hayward S244T2 24” Sand Filter
Hayward 1hp Super Pump 2 speed
Raypak PR266 EN 266,000 btu, Electronic & Digital Natural Gas Heater
AquaRite Salt Chlorine Generating System
Aqualamp Lighting System (2 x LED) w/ remote
Lock-in Fitted Winter Cover
Acrylic Step Cover 6ft
Extra Water Line for Pool Cleaner
Maintenance Kit:
Deluxe Vacuum Hose (35’ length) Deluxe Vacuum Head
Deluxe Telescopic Pole (8’ - 16’) Deluxe Leaf Skimmer
Stainless Steel 3 Tread Ladder Deluxe Thermometer
Pool Installation
Excavation w Backhoe Excavator & Fill Removal using a Bobcat (as a second machine)
Leveling and Concreting the Steel Walls using 3000 psi Concrete
Three Stage Hard Bottom:
1st Stage - Gravel (3/4” Clear Stone) 4 - 6” Thickness
2nd Stage - Concrete (3000 psi) 4” Thickness
3rd Stage - Vermiculite Coating 1” Thickness
Plumbing the Pool to the Filtration Equipment with 2” Flex PVC or Polyethelyne Piping
Plumbing of Filtration Equipment and any Aboveground Plumbing with Schedule 40 Rigid PVC
Back Fill with 3/4” Clear Stone or Granular “A”
Concrete Deck (3’ width) 4000 psi, Air-entrained Concrete 4 - 5” Thickness
Re-inforced with 6 X 6 Steel Mesh, or Rebar (Where needed or Applicable)
Deck is Supported on Double “A” Deck Frame System
Self-drawn plan / design:

Day 1: Excavation. Weather is calling for thunderstorms so not sure if they will be done today or get stopped due to rain.