Pool math is telling me to add 5.1 gal of MA. I'm not opposed to that figure, I'm just worried about adding that much all at once. I'm also concerned about adding the MA and the chlorine at the same time. Seems I read (here I think) that I should wait a period of time between adding the MA and the chlorine. Here are my numbers (target values based on Pool Math calculations): Pool Math is also telling me to replace 11% (3K gal) of the water. I'm thinking that I should replace the water first, then retest. Any suggestions? thanks
NOW - Target
FC 2 - 4
pH 10 - 7.5
TA 230 - 100
CH 270 - 300
CYA 45 - 40
NOW - Target
FC 2 - 4
pH 10 - 7.5
TA 230 - 100
CH 270 - 300
CYA 45 - 40