More progress...we almost had water in the pool last week but due to misdelivered spa fittings we had to reschedule the plaster...hopefully for sometime next week. In the meantime, a lot more things are coming together although still a lot of things left to do and lots of details. But here are a few pics of some progress:
First, we finally were able to connect the fire pit...there were some electrical issues but those were worked out today. Still need to figure out what we're going to put on it -- most likely rounded lava rock to match the black rounded pebble we're putting in the gaps between the tile and pavers.
You can make out the bbq area a bit in the left of that pic so here is a photo showing more of that...
It is hard to make out in the photo above but you can see the top of the outdoor shower head which is behind the bbq wall...a couple more shower area pics below:
My wife was not a fan of my choice to do the shower...until she saw it finished. The gates are just drop dead gorgeous and the wood in general came out just awesome. We need to add the pebble around the base and get a few niceties in place (a small stool, shelf and maybe a towel rack) but the wife and kid already love it. First time the wife came back from the beach and realized she can easily get the sand off the boy before tracking it through the house and she was sold.
And some pics from the equipment pad:
The intellicenter is hooked up and I can use it to start the fire pit which is nice...but really need the pool to get plastered and the aquabrite put on!!! We just went through the worst heat wave this year and it was quite disappointing not to be able to jump in the pool...but, we're getting there at least.
The plants are also mostly in which has made a huge difference. They'll need a couple years to really start to fill in but just having plants around is great. I don't have great pics of it, but you can make out some green in this next pic which is of the partially constructed water/fire feature in our courtyard:

The main soapstone slabs were put on last week. The middle section will have water running down it and the bottom basin, which will also be finished in soapstone, will have a linear burner in it. Expecting this feature to get finished this week so hopefully I'll have a better pic soon.
Hoping to hang the outdoor movie screen this week...plaster/aquabrite go on next week...I think with aquabrite we should be able to get in the water pretty quickly so we could be swimming in a few short weeks!
After that, it should just be some details...the artificial turf, automatic pool cover, landscaping pebble/stones and a bit more planting. There is a light at the end of this looooooooong tunnel. Having a grill (and a Costco membership) has made the past month a heck of a lot more tolerable!