First off, thank you to everyone for keeping this wonderful resource up and running. I really wish I had found this site sooner! But now that I'm here, I thought I'd throw up my build to see what everyone thinks about it. It's not a big pool, just enough to cool off in this Texas heat.
Pool Description:
Equipment(all Hayward):
Timeline so far:
May, 2021 - "Honey, I want a pool"
July 2021 - Moved into new house
Early Dec - Pool builder selected
Dec 14th - Design finalized
Jan 3rd - Design finalized for real
Jan 20th - HOA approval
Jan 27th - Big dig
Jan 28th - Steel
Jan 31st - Short stub plumbing
Feb 1st - Gunite
Feb 2nd - Plumbing started
Feb 3rd - Change to SWG, thanks TFP
Feb 4th - Equipment delivered
Feb 7th - Plumbing
Feb 11th - Electrical
Feb 12th - Tile/coping
Feb 18th - Deck formwork, drainage
Feb 25th - Deck concrete
Mar 5th - Plaster
Mar 7th - Acid wash and fill with water
Mar 12th - Spray deck texture and paint
Mar 13th - First beer by the pool
Mar 23rd - Call gas company to upgrade meter
Apr 2nd - First official swim
Apr 9th - Yard drainage installed
Apr 15th - Salt added
Apr 20th - Leak confirmed
May 4th - Gas hookup
June 1-4th - Leak repair
Rendering is before we extended the tanning ledge and redesigned the back wall


Pool Description:
- 11'8" x 28'6" Gunite SWG pool, 3.5' to 5.5' depth, ~8500 gallons
- 6' x 10'5" tanning ledge
- 7' x 7' elevated spa with reverse negative edge spillway
- Bubblers, waterfalls, elevated rear wall
- PebbleSheen Blue Surf
- Glass Tile waterline
- Travertine Coping
- 500s.f. of concrete deck with spray finish
Equipment(all Hayward):
- Pump - Tristar VS 950 2.7HP
- Filter - W3C5030, 525s.f.
- Heater - W3H400FDN, 400k BTU
- Control - OmniPL
- SWG - TCELL940
- Cleaner - Polaris Alpha IQ+
- Anything major I'm missing here?
Timeline so far:
May, 2021 - "Honey, I want a pool"
July 2021 - Moved into new house
Early Dec - Pool builder selected
Dec 14th - Design finalized
Jan 3rd - Design finalized for real
Jan 20th - HOA approval
Jan 27th - Big dig
Jan 28th - Steel
Jan 31st - Short stub plumbing
Feb 1st - Gunite
Feb 2nd - Plumbing started
Feb 3rd - Change to SWG, thanks TFP
Feb 4th - Equipment delivered
Feb 7th - Plumbing
Feb 11th - Electrical
Feb 12th - Tile/coping
Feb 18th - Deck formwork, drainage
Feb 25th - Deck concrete
Mar 5th - Plaster
Mar 7th - Acid wash and fill with water
Mar 12th - Spray deck texture and paint
Mar 13th - First beer by the pool
Mar 23rd - Call gas company to upgrade meter
Apr 2nd - First official swim
Apr 9th - Yard drainage installed
Apr 15th - Salt added
Apr 20th - Leak confirmed
May 4th - Gas hookup
June 1-4th - Leak repair
Rendering is before we extended the tanning ledge and redesigned the back wall


Last edited: