I have 150 amp main panel service. A generic load calc on my house is about 65 amps and rounded up gives me 80amps (2300 sq ft home with electric wall oven and stovetop and electric dryer). I planned on installing a 100amp sub panel for the the pool. The pool will have a VSP a heat pump and a SWCG, single light, and an aux outlet.
I assume if I was running everything in my house; dryer, two ovens, stove top, all lights, 4 window AC units, every tool I own, plus the pool heater, pump and lights, I would be close to exceeding my total main panel load.
I’m still in the planing stages with PB, but I’m trying to get a sense if I will need a service upgrade. Thoughts?