Hello,
Just curious as to what the real process is supposed to be or what others have seen with their pools. We have spoken to about 6 different pool builders. The last one we spoke with today said we should wait 28 days after shooting the gunite before proceeding. He is saying due to this it takes him about 3 months to do a pool vs. 5 to 6 weeks other companies are quoting. What have you all seen with your pool builds or is the wait period a real thing that people dont do?
Thanks
Just curious as to what the real process is supposed to be or what others have seen with their pools. We have spoken to about 6 different pool builders. The last one we spoke with today said we should wait 28 days after shooting the gunite before proceeding. He is saying due to this it takes him about 3 months to do a pool vs. 5 to 6 weeks other companies are quoting. What have you all seen with your pool builds or is the wait period a real thing that people dont do?