Update: walls are up and plumbing is almost complete. It appears they are going to pour the collar on top of the plumbing. Is this okay?


***************************
Hi,
New here. In the process of having a 16x32 vinyl/steel wall pool installed. Found this forum a bit late (after signing contract) but it has been super helpful.
Some background: Of the three quotes I got last summer all three said they would backfill with the excavated dirt so I didn’t question it. Learned after that 3/4 gravel is ideal. I asked my PB (very late) if he could backfill with gravel and how much it would cost. He told me he doesn’t do that and it wasn’t an option. I explained why I wanted that and he said he compacts during backfill and will install sonotubes if I like. He also said I can wait as long as I like to install concrete (3ft included) and I will have an opportunity to discuss that with the mason. During excavation there were a lot of roots which he did his best to keep separate (large pile in the back) which I will dispose of. I plan to also go through the backfill dirt and pulling out anything else I see.
Getting ahead of myself here but, should I still wait until next year to pour the patio? It would be about 1000 sq ft.



***************************
Hi,
New here. In the process of having a 16x32 vinyl/steel wall pool installed. Found this forum a bit late (after signing contract) but it has been super helpful.
Some background: Of the three quotes I got last summer all three said they would backfill with the excavated dirt so I didn’t question it. Learned after that 3/4 gravel is ideal. I asked my PB (very late) if he could backfill with gravel and how much it would cost. He told me he doesn’t do that and it wasn’t an option. I explained why I wanted that and he said he compacts during backfill and will install sonotubes if I like. He also said I can wait as long as I like to install concrete (3ft included) and I will have an opportunity to discuss that with the mason. During excavation there were a lot of roots which he did his best to keep separate (large pile in the back) which I will dispose of. I plan to also go through the backfill dirt and pulling out anything else I see.
Getting ahead of myself here but, should I still wait until next year to pour the patio? It would be about 1000 sq ft.