Going to keep this short and sweet -
September 25th Contract signed
November 3rd Dig started and finished
November 4th Rebar in the morning / Plumbing in the afternoon
November 5th Plumbing 'done' but will come back and do the outflow trench and other stuff. Electrician out. Trenches filled.
November 6th City Inspection
November 8th Gunite Inspection
Test Kit Ordered - Arrived in six days
November 16th Gunite poured -- Another pool build in the area and they are doing ours after!
Gas line dug by the plumbers - Encountered problems with another sprinkler line
November 17th Gunite crew and finishers arrived at 6:30AM and worked until around 3PM. Stairs and bench along with taking off some of the forms from yesterday's pour. All mess and scraps cleaned up and stacked in a pile.
November 18th One guy came today and pulled off the remaining forms. Watering beginning on the gunite. Plumbers back and running the pipe / gas line. Trenches still open for city inspection either today or tomorrow morning. Electrician out to install the pool light (which we never wanted, didn't have in the contract, but they insisted for safety so the pool builder is paying for it) Watering the pool pad, too.
Watering the gunite was five days, pool builder said to water twice a day for half an hour. Sometime around here the build manager had men come back and fill in the gas line trench. They said no more digging on that side yard.
November 23rd Two tiles guys came with the wrong tile. They set up shop, painted some blue green water sealer where the tile will go, and left. Thankfully I caught the mistake and spent time with the designer and our build manager to get the right tile. They made a special trip to Houston to bring back the right stuff.
November 24th and 25th -- Waterline tile and columns done, the day before Thanksgiving they did the tile on the top step and grouted.
December 4th - Decking rebar started - Maybe. It's super muddy due to off and on rain.
Okay, lost in the shuffle of December! We had one load of dirt delivered and needed another due to loss during the rain. The rebar was set down for the coping / decking.
December 29th Concrete poured - Column caps, decking and coping together. New larger pad poured after the gunite one was torn up and discarded. Plumbers set up the equipment on the pads but didn't hook them up. Some forms removed that day, some the next day.
January 4th - Electricians by.
----------------------------------------------------
Preliminary work was removing the sprinkler system in the back. Fencing to keep the dogs out of the build area.
Relocating some plants. All this was done by us -- Our landscaping contact ghosted after they installed a side gate.
Note on the design -- The first step is out of the water. It's completely covered with an unglazed Aqua Bella off white 2" tile. (Non-skid)
The gaps near the house are for drainage. Finish is primera stone wet edge Sky Blue Treasure. Tile pictured is Master Tile Isola Elba 6" (waterline) and Isola Sardinia 2" (Small columns)
September 25th Contract signed
November 3rd Dig started and finished
November 4th Rebar in the morning / Plumbing in the afternoon
November 5th Plumbing 'done' but will come back and do the outflow trench and other stuff. Electrician out. Trenches filled.
November 6th City Inspection
November 8th Gunite Inspection
Test Kit Ordered - Arrived in six days
November 16th Gunite poured -- Another pool build in the area and they are doing ours after!
Gas line dug by the plumbers - Encountered problems with another sprinkler line
November 17th Gunite crew and finishers arrived at 6:30AM and worked until around 3PM. Stairs and bench along with taking off some of the forms from yesterday's pour. All mess and scraps cleaned up and stacked in a pile.
November 18th One guy came today and pulled off the remaining forms. Watering beginning on the gunite. Plumbers back and running the pipe / gas line. Trenches still open for city inspection either today or tomorrow morning. Electrician out to install the pool light (which we never wanted, didn't have in the contract, but they insisted for safety so the pool builder is paying for it) Watering the pool pad, too.
Watering the gunite was five days, pool builder said to water twice a day for half an hour. Sometime around here the build manager had men come back and fill in the gas line trench. They said no more digging on that side yard.
November 23rd Two tiles guys came with the wrong tile. They set up shop, painted some blue green water sealer where the tile will go, and left. Thankfully I caught the mistake and spent time with the designer and our build manager to get the right tile. They made a special trip to Houston to bring back the right stuff.
November 24th and 25th -- Waterline tile and columns done, the day before Thanksgiving they did the tile on the top step and grouted.
December 4th - Decking rebar started - Maybe. It's super muddy due to off and on rain.
Okay, lost in the shuffle of December! We had one load of dirt delivered and needed another due to loss during the rain. The rebar was set down for the coping / decking.
December 29th Concrete poured - Column caps, decking and coping together. New larger pad poured after the gunite one was torn up and discarded. Plumbers set up the equipment on the pads but didn't hook them up. Some forms removed that day, some the next day.
January 4th - Electricians by.
----------------------------------------------------
Preliminary work was removing the sprinkler system in the back. Fencing to keep the dogs out of the build area.
Relocating some plants. All this was done by us -- Our landscaping contact ghosted after they installed a side gate.
Note on the design -- The first step is out of the water. It's completely covered with an unglazed Aqua Bella off white 2" tile. (Non-skid)
The gaps near the house are for drainage. Finish is primera stone wet edge Sky Blue Treasure. Tile pictured is Master Tile Isola Elba 6" (waterline) and Isola Sardinia 2" (Small columns)
Attachments
-
Data2020.jpg131.5 KB · Views: 189
-
PoolMeasurements2020.jpg157.6 KB · Views: 266
-
PoolBuild1.jpg182.7 KB · Views: 266
-
Poolbuild2.jpg177.5 KB · Views: 244
-
masisoelb-6-799x800-IsolaElba-MasterTile.jpg323.5 KB · Views: 200
-
Masisosar-MOS2-MT.jpg283 KB · Views: 187
-
10-24-20Sprinklers.jpg277.8 KB · Views: 189
-
10-24-20Sprinklers-2.jpg250.1 KB · Views: 177
Last edited: