Hi all, first post. Signed contract on 5/5 after getting bids from too many builders. Did not close until 5/25 because of holdups at the title company. Dig and steel 6/1. Gunite & rough plumbing 6/2. Set equipment 6/3. Rock waterfall & rock beam 6/4. Plumbing 6/9. Coping & tile 6/10. Electrician 6/13. Plaster and decking still to come.
Equipment:
Pentair DE filter
Pentair whisper flo
Easy touch 8 with wireless remote
Polaris w booster pump
IntelliChlor
Pentair minimax 400,000
Delzone Ozone
http://s810.photobucket.com/albums/zz26/heathshluler/pool dig/