Hello all! First time poster, recent lurker. I appreciate all of the topics and responses from this website. Pool ownership is definitely intimidating and this site has been very helpful in answering my questions.
I am faced with a question about bonding that hopefully someone can help me with.
We recently completed construction of a new inground Fiberglass pool, 35' x 15.5', 14,708 gallons. When they were pouring the surrounding concrete, they had gotten 3/4th of the way around when I had noticed that there was a copper wire that was left hanging into the pool. Later did I find out that this was the bonding wire. They wound up digging out the wet concrete and tying in the bonding wire to the rebar. The other end of the bonding wire appears properly connected to the heater, pump, and there is a connection to the water via a plug in the return line.
I'm worried about the connection to the rebar. I'm assuming that 4 connections were made, but I'm not entirely sure as I'm learning about bonding and equipotential after the fact. I'm also pretty sure they did not use any bonding clamps, rather just tied into the rebar like a twist tie.
My questions:
1. Is there any way to test the bonding wire to see if equipotential is reached?
2. We are planning to place travertine pavers on top of the existing concrete surround - should there be a bonding grid in between the concrete and the pavers? In case the concrete bonding connection was not good, would adding a bonding grid between the paver and concrete serve as a "backup" for equipotential?
Thanks in advance!
I am faced with a question about bonding that hopefully someone can help me with.
We recently completed construction of a new inground Fiberglass pool, 35' x 15.5', 14,708 gallons. When they were pouring the surrounding concrete, they had gotten 3/4th of the way around when I had noticed that there was a copper wire that was left hanging into the pool. Later did I find out that this was the bonding wire. They wound up digging out the wet concrete and tying in the bonding wire to the rebar. The other end of the bonding wire appears properly connected to the heater, pump, and there is a connection to the water via a plug in the return line.
I'm worried about the connection to the rebar. I'm assuming that 4 connections were made, but I'm not entirely sure as I'm learning about bonding and equipotential after the fact. I'm also pretty sure they did not use any bonding clamps, rather just tied into the rebar like a twist tie.
My questions:
1. Is there any way to test the bonding wire to see if equipotential is reached?
2. We are planning to place travertine pavers on top of the existing concrete surround - should there be a bonding grid in between the concrete and the pavers? In case the concrete bonding connection was not good, would adding a bonding grid between the paver and concrete serve as a "backup" for equipotential?
Thanks in advance!