We just finished having our pool built and the pebble sheen finish installed on May 3rd. I noticed when the installation crew was doing the finish , they did the walls first. After the walls were done, they cut out the last few inches on the bottom of the wall after the transition so there was an even layer to finish the bottom to. Well when troweling the bottom to that seam, they left a very noticeable transition. Is this normal? Also Thursday May 12, 9 days after installation I noticed 2 small chips in the bottom. Alittle smaller then the size of a dime. I can see the concrete shell through them. How should this be properly fix? This pebble sheen layer looks extremely thin, is this the standard?