Hey folks,
Up here in the great white. I have taken on to build my own pool and its the very first one for me. I have used 8" core ICF and built buttress walls in the deep end. To make a long story short My pour set up way to fast for me to trowel my concrete smooth. I am in the process of contracting out maybe an over pour?? To get it all smooth. Have looked into using Meadow patch as well.
So I have a few questions to ask the forum.
Would you concrete guys recommend a patch or an overopour? (see pictures)
And has anyone used sider crete in the north? pros cons?
Has anyone had experience with using sika 107 ? I have seen one in my area that has worked for three seasons without fail.
What other products are available to seal both the ICF and Styrofoam?
Before you say why not drop in a vinyl liner notice that I poured a giant concrete step that has made this not possible. and I would still have to manage my honeycombed slope.
Any advice skilled or not appreciated.


Up here in the great white. I have taken on to build my own pool and its the very first one for me. I have used 8" core ICF and built buttress walls in the deep end. To make a long story short My pour set up way to fast for me to trowel my concrete smooth. I am in the process of contracting out maybe an over pour?? To get it all smooth. Have looked into using Meadow patch as well.
So I have a few questions to ask the forum.
Would you concrete guys recommend a patch or an overopour? (see pictures)
And has anyone used sider crete in the north? pros cons?
Has anyone had experience with using sika 107 ? I have seen one in my area that has worked for three seasons without fail.
What other products are available to seal both the ICF and Styrofoam?
Before you say why not drop in a vinyl liner notice that I poured a giant concrete step that has made this not possible. and I would still have to manage my honeycombed slope.
Any advice skilled or not appreciated.