Let me start by saying that we had an issue which resulted in our spa being slightly rotated. This was most noticeable on the spillway. The PB jackhammered out the spillway and reconstructed it from rebar to plumbing. However, after gunite, there are areas of exposed rebar and plumbing. Upon further inspection of the whole pool, I'm seeing several areas where the bonding beam rebar is exposed. Looking back at an old photo before gunite, I can see that the rebar was set up against the forms. So it seems like no surprise that there's exposure. My understanding that all rebar should be encased by at least 3" of gunite. Any opinions?
Thanks in advance,
Edward
Thanks in advance,