Hi all,
I'm shallowing out my +20K gallon kidney shaped pool. The pool has an open stress crack at the outer bend and has been empty for a couple years aging several additional cracks throughout. The PB will be opening and repairing cracks as needed once the plaster is off and they get a better look at the shell.
The whole bottom from shallow to deep will be rebarred and shotcreted and blended into the walls.
My concern is this:
The deep end will go from 9' to 5'6".
The shallow end will go from 3" up to a 6" sun shelf from wall to wall extending about 8' into the pool. From sun shelf to deep end there will be roughly 12"cover sloping down to the 5'6". There will be a tremendous weight in the shallow and in the deep end from the amount of shotcrete. Will this make for a weak STRESS joint in the middle around the kidney turn?? PB says not to worry.
As added strength I'm adding a seat bench completely around the outer bend of the kidney.
Should all rebar be 9" grid?
I recognize I'll get responses to consult an SEOR but just wanted some experience in here first.
I'm a couple weeks away from the build and could use any thoughts sooner than later.
Many, many thanks!
I'm shallowing out my +20K gallon kidney shaped pool. The pool has an open stress crack at the outer bend and has been empty for a couple years aging several additional cracks throughout. The PB will be opening and repairing cracks as needed once the plaster is off and they get a better look at the shell.
The whole bottom from shallow to deep will be rebarred and shotcreted and blended into the walls.
My concern is this:
The deep end will go from 9' to 5'6".
The shallow end will go from 3" up to a 6" sun shelf from wall to wall extending about 8' into the pool. From sun shelf to deep end there will be roughly 12"cover sloping down to the 5'6". There will be a tremendous weight in the shallow and in the deep end from the amount of shotcrete. Will this make for a weak STRESS joint in the middle around the kidney turn?? PB says not to worry.
As added strength I'm adding a seat bench completely around the outer bend of the kidney.
Should all rebar be 9" grid?
I recognize I'll get responses to consult an SEOR but just wanted some experience in here first.
I'm a couple weeks away from the build and could use any thoughts sooner than later.
Many, many thanks!