UPDATE - We finally got started on this project. Link below to later post in the thread:
www.troublefreepool.com
Builder: Aquaterra (best combination of bid+ experience +design aesthetic alignment)
—————————
Excavation - June 28 to July 8
Drilling piers - Unfortunately, drilling for concrete piers hit ground water at 9 feet, so had to redo the engineering and also switch to like 40 helical piers (increased cost +++, of course, also excavation cost of 2x).
Rough stub plumbing and electrical - July 16 to July 28
Rebar (double matte) - July 18 to July 27 - extended to August 2 to increase basin depths and then more work through august then to sept to work through new engineering certifications plus deal with cave-ins from excessive rain
Gunite 12" walls and floors - September 30
Gunite waterproofing and yard grading - October 4
Long gas lines run - Oct 9
Long plumbing and stub electrical, cut channel for acrylic panel - Oct 13
Acrylic panel installed - Oct 18
Electrical inspection - Oct 20
Basecrete application and begin feature wall and in step pad bases - Oct 20
Tile and Cabana framing - Nov-Dec
Deck framing and gravel done - Jan 2023
Drainage done and tied in - Jan 2023
Surge basin concrete cap done - Jan 2023
Footers poured - Jan 2023
Retaining wall excavation started - Jan 2023
Sport court excavation underway - rebar is next - Jan 2023
Sport court slab and retaining wall completed - Feb 2023
Waterproofing of feature wall and planters - Feb 2023
Deck in progress - Feb 2023
Mostly tile work - March 2023
- Feature wall tile in process
- In pool planters
- Fire pit surround tile
- Finish waterline tile
April 2023
- Grading, and more grading.
- Concrete pads formed up
- Rear steps roughed out
- Cabana step downs roughed in
- Infratech WD60 heaters and flush mounts boxed in (2 in cabana, 4 in existing patio)
- Existing patio demoed for new tongue and groove ceiling.
- Cabana cabinets roughed in
- Various tile work continues
May 2023
- concrete work, pads, and bases
- 24 foot water fall fixture
- stone step pads
- sport court installed
- stucco retaining and feature walls
July 2023
- pre plaster shell prep, cleaning and fittings
- landscaping started (beds, retaining walls, holly trees planted)
- irrigation almost done
- screening fences started
- cabana coming along finally (stucco in process, counters installed, and counter face tile done, t&g ceiling done, shade structure in fabrication)
- t&g ceiling done in existing patio
- plaster and acid wash
——————————
Howdy, y'all. We are are in DFW and we are bidding out our pool/backyard. I have been following this board intently as we finally finished design (fourth designer was the charm)
Sorry, I don't have render shots. I only have a screenshot of the plans and the video link (
).
Advice, criticism and thoughts all solicited and welcome. We have one bid and it's pretty shocking (attached). We will be getting two more. Thoughts?

Dallas (Southlake) Area New Build - July 2022 - Construction Thread
UPDATE - We finally got started on this project. Link below to later post in the thread: https://www.troublefreepool.com/threads/dallas-southlake-area-new-build-july-2022.258167/#post-2256273 Builder: Aquaterra (best combination of bid+ experience +design aesthetic alignment) —————————...

Builder: Aquaterra (best combination of bid+ experience +design aesthetic alignment)
—————————
Excavation - June 28 to July 8
Drilling piers - Unfortunately, drilling for concrete piers hit ground water at 9 feet, so had to redo the engineering and also switch to like 40 helical piers (increased cost +++, of course, also excavation cost of 2x).
Rough stub plumbing and electrical - July 16 to July 28
Rebar (double matte) - July 18 to July 27 - extended to August 2 to increase basin depths and then more work through august then to sept to work through new engineering certifications plus deal with cave-ins from excessive rain
Gunite 12" walls and floors - September 30
Gunite waterproofing and yard grading - October 4
Long gas lines run - Oct 9
Long plumbing and stub electrical, cut channel for acrylic panel - Oct 13
Acrylic panel installed - Oct 18
Electrical inspection - Oct 20
Basecrete application and begin feature wall and in step pad bases - Oct 20
Tile and Cabana framing - Nov-Dec
Deck framing and gravel done - Jan 2023
Drainage done and tied in - Jan 2023
Surge basin concrete cap done - Jan 2023
Footers poured - Jan 2023
Retaining wall excavation started - Jan 2023
Sport court excavation underway - rebar is next - Jan 2023
Sport court slab and retaining wall completed - Feb 2023
Waterproofing of feature wall and planters - Feb 2023
Deck in progress - Feb 2023
Mostly tile work - March 2023
- Feature wall tile in process
- In pool planters
- Fire pit surround tile
- Finish waterline tile
April 2023
- Grading, and more grading.
- Concrete pads formed up
- Rear steps roughed out
- Cabana step downs roughed in
- Infratech WD60 heaters and flush mounts boxed in (2 in cabana, 4 in existing patio)
- Existing patio demoed for new tongue and groove ceiling.
- Cabana cabinets roughed in
- Various tile work continues
May 2023
- concrete work, pads, and bases
- 24 foot water fall fixture
- stone step pads
- sport court installed
- stucco retaining and feature walls
July 2023
- pre plaster shell prep, cleaning and fittings
- landscaping started (beds, retaining walls, holly trees planted)
- irrigation almost done
- screening fences started
- cabana coming along finally (stucco in process, counters installed, and counter face tile done, t&g ceiling done, shade structure in fabrication)
- t&g ceiling done in existing patio
- plaster and acid wash
——————————
Howdy, y'all. We are are in DFW and we are bidding out our pool/backyard. I have been following this board intently as we finally finished design (fourth designer was the charm)
Sorry, I don't have render shots. I only have a screenshot of the plans and the video link (
Advice, criticism and thoughts all solicited and welcome. We have one bid and it's pretty shocking (attached). We will be getting two more. Thoughts?

|
Last edited: