My pool was plastered with Luna Quartz Pacific at the beginning of June. This is what my pool looked like. The PB came out and said this will clear up and I will love it. IF not they would do a Hot Start at the end of August to clear it up. No worries! DJI_0029.JPG
They just finished the Hot Start with little success. A Hot Start was dumping muriatic Acid in pool with a pump in pool circulating. They came out every day to brush. They then drained the Spa into the pool and did a acid bath on the spa. No change.

IMG_5955.JPG
Here is the spa after the acid wash. The place that is circled is where he polished to see if that works. Looks Like polishing would bring out the right color and give me a smooth surface.
So at this point the PB is going to discuss our options. Looks like it is either polishing entire pool or a redo. This was a reno and I do not want another coat on top of this coat. I would have to insist on a chip out.
Should I go with the polish?
 
Your PB should have started with the polish.

The acid bath just weakened your plaster. But that is water under the bridge.

Polish is the correct fix.
 