AQUA~HOLICS
In The Industry
My plumber likes to show up after rebar has been installed.
Good stuff Dave and just in time. I'll role out the first pass with this input and use sub project features so a simple view is always available.Schedules can quickly grow to so many tasks and relationships it can get overwhelming and even a little confusing.
Let's break this down into chunks, starting with construction activities. This is for my planned IG gunite pool (30x16).
The tasks below represent durations for on-site work only. The sequence and task durations are my guesses, based on reading many build threads here, but never having built a pool. Are any tasks out of typical order? Should any additional tasks be added? Are the durations decent?
Layout Pool, Equipment Pad, Plumbing Runs 1 day
Call Arizona 811 to Dig 5 days
Review and confirm layout 1 day
Excavation 3 days
Rough Plumbing 3 days
Steel/Rebar 2 days
Rough Electrical 2 days
Shotcrete 1 day
Masonry Water/Fire Features 3 days
Waterline & Accent Tile 2 days
Fencing/Barriers 2 days
Finish Electric 2 days
Finish Plumbing 2 days
Coping (paver) 3 days
Clean-up & Prep for plaster 2 days
Plaster 1 day
Initial Fill 1 day
There are lots of other activity groupings to deal with design, permitting/HOA approval, bidding, equipment, coordination, that we can address in later posts.
Dave,Schedules can quickly grow to so many tasks and relationships it can get overwhelming and even a little confusing.
Let's break this down into chunks, starting with construction activities. This is for my planned IG gunite pool (30x16).
The tasks below represent durations for on-site work only. The sequence and task durations are my guesses, based on reading many build threads here, but never having built a pool. Are any tasks out of typical order? Should any additional tasks be added? Are the durations decent?
Layout Pool, Equipment Pad, Plumbing Runs 1 day
Call Arizona 811 to Dig 5 days
Review and confirm layout 1 day
Excavation 3 days
Rough Plumbing 3 days
Steel/Rebar 2 days
Rough Electrical 2 days
Shotcrete 1 day
Masonry Water/Fire Features 3 days
Waterline & Accent Tile 2 days
Fencing/Barriers 2 days
Finish Electric 2 days
Finish Plumbing 2 days
Coping (paver) 3 days
Clean-up & Prep for plaster 2 days
Plaster 1 day
Initial Fill 1 day
There are lots of other activity groupings to deal with design, permitting/HOA approval, bidding, equipment, coordination, that we can address in later posts.
On your schedule layout I noticed no dates for city inspection. I advise customers to have one or two days open after the inspection dates for corrections if needed, especially before Shotcrete.
Good point and thanks for the input!The number one reason my plumber insists on starting after rebar is one less trade coming after his work and less chances of damage to his work. He sometimes has to re-bend some of the cage for his main drain lines with a hickey bar but he feels that’s a good trade off.
On your schedule layout I noticed no dates for city inspection. I advise customers to have one or two days open after the inspection dates for corrections if needed, especially before Shotcrete. Keep in mind if you have to cancel last minute on a date and reschedule that crew will most likely not work at all that day.