Hi All
I have a super sub pump and just started draining 3/4 of the pool to reduce the CYA levels - it will be filling in less than 3 hours so I'd like to ask about the new chemicals I put in.
I just received the TF-100 today and already familiarized myself with all the tests on the old pool water.
My plan is to begin with 3 gallons of liquid CYA (with filter running) which I already have...
Wait 24 hours with filter running entire time and then add...
2 qts. of Muriatic Acid (diluted in water first) with filter running - wait 4 hours and then add...
4 gallons of Liquid Chlorine 10% solution and after 12 hours...
test all chems - esp CYA levels which no doubt will need to be raised
I'd like to hear from the experienced ones - thoughts / comments / advice?
Thank you for being such patient people
I have a super sub pump and just started draining 3/4 of the pool to reduce the CYA levels - it will be filling in less than 3 hours so I'd like to ask about the new chemicals I put in.
I just received the TF-100 today and already familiarized myself with all the tests on the old pool water.
My plan is to begin with 3 gallons of liquid CYA (with filter running) which I already have...
Wait 24 hours with filter running entire time and then add...
2 qts. of Muriatic Acid (diluted in water first) with filter running - wait 4 hours and then add...
4 gallons of Liquid Chlorine 10% solution and after 12 hours...
test all chems - esp CYA levels which no doubt will need to be raised
I'd like to hear from the experienced ones - thoughts / comments / advice?
Thank you for being such patient people